GreenH2 Fertiliser — Financial Plan

The key assumptions, the projected income statement, balance sheet and cash-flow statement, the capital-cost build, the debt-service coverage, the sensitivity and scenario analysis, the valuation and the returns summary underpinning GreenH2.

GreenH2 Fertiliser Business PlanSection 13 › Financial Plan

Section 13 · Business Plan

Financial Plan

The key assumptions, the projected income statement, balance sheet and cash-flow statement, the capital-cost build, the debt-service coverage, the sensitivity and scenario analysis, the valuation and the returns summary underpinning GreenH2.

All figures in this section derive from a single integrated financial
model in which the income statement, balance sheet and cash-flow
statement fully reconcile, and the balance sheet balances to zero in
every projection year. The model spans ten years: three years of
development and construction (pre-revenue), commissioning in Year 4, and
a ramp to full nameplate output by Year 6. Returns are presented on both
a project (unlevered) and an equity (levered) basis.

13.1 Key assumptions

Table 13. Principal modelling
assumptions.

Assumption Value
Projection horizon 10 years (Years 1–10)
Commissioning / full output Year 4 (40%) → Year 6 (100%)
Urea capacity / price 900,000 t p.a. @ R8,000/t (base)
Merchant ammonia capacity / price 700,000 t p.a. @ R7,500/t (base)
Ammonium nitrate capacity / price 500,000 t p.a. @ R9,000/t (base)
Price escalation 4.0% per annum (nominal)
Cost escalation 4.5% per annum (nominal)
Corporate tax rate 27% (South Africa), with loss carry-forward
Senior debt rate / tenor 11.8% all-in / 12-year amortisation
Gearing (debt : equity) ~60% : ~40%
Discount rate (project NPV) 14.5%
Depreciation Straight-line over 22 years

13.2 Capital cost and funding

Total funded cost is approximately R37 billion: around R32 billion of
hard EPC and owner’s cost, plus interest during construction, working
capital and reserves. Funding is structured as roughly 60% senior
project debt and 40% equity, of which this R5.0 billion seed round forms
the development tranche drawn first.

Figure 5
Figure 5 — Project funding structure — senior debt and equity (with the R5.0bn seed tranche identified).
Figure 6
Figure 6 — Hard capital-expenditure phasing across the four-year development and construction period.

Table 14. Hard capital cost by plant area (R
billion).

Plant area Capital Share
Gasification & syngas units R7.00bn 22%
Ammonia synthesis plant R8.50bn 27%
Urea plant R4.50bn 14%
Ammonium nitrate & nitric acid R3.00bn 9%
Carbon capture facilities R3.00bn 9%
120 MW solar & grid connection R1.80bn 6%
Storage, rail & site infrastructure R2.20bn 7%
Owner’s costs, EPC margin & contingency R2.00bn 6%
Total hard capital cost R32.00bn 100%
Figure 7
Figure 7 — Distribution of the R32bn hard capital cost across the integrated complex.

13.3 Projected income statement (operating years)

Table 15. Summary income statement, Years 4–10
(R billion).

R bn Y4 Y5 Y6 Y7 Y8 Y9 Y10
Revenue 7.2 13.1 19.5 20.3 21.1 21.9 22.8
Cost of sales -5.5 -7.9 -11.0 -11.5 -11.9 -12.4 -12.9
Gross profit 1.7 5.2 8.5 8.8 9.2 9.5 9.9
Operating expenses -0.7 -0.9 -1.1 -1.2 -1.2 -1.3 -1.3
EBITDA 1.0 4.3 7.4 7.6 7.9 8.2 8.6
Depreciation -1.4 -1.4 -1.4 -1.4 -1.4 -1.4 -1.4
EBIT -0.4 2.9 5.9 6.2 6.5 6.8 7.1
Net interest -1.4 -2.7 -2.7 -2.4 -2.2 -2.0 -1.8
Profit before tax -1.8 0.2 3.2 3.8 4.3 4.8 5.3
Taxation -0.4 -1.0 -1.2 -1.3 -1.4
Net profit after tax -1.8 0.2 2.8 2.7 3.1 3.5 3.9
EBITDA margin 14% 33% 38% 38% 38% 38% 38%
Figure 8
Figure 8 — From revenue to net profit at full production (Year 6), showing the cost, financing and tax bridge.
Figure 9
Figure 9 — EBITDA and EBITDA margin — margins expand as fixed costs are absorbed across rising volume.

13.4 Projected balance sheet (selected years)

The balance sheet balances precisely in every year. During
construction, property, plant and equipment accumulates as capital is
deployed and interest is capitalised; from Year 4 the asset depreciates
while retained earnings build and senior debt amortises from Year 6.

Table 16. Summary balance sheet, selected years
(R billion).

R bn Y3 Y4 Y5 Y6 Y8 Y10
Cash & equivalents 2.0 3.6 4.4 5.9 10.7 16.9
Receivables & inventory 1.6 2.7 3.9 4.2 4.6
Property, plant & equipment 19.6 31.2 29.8 28.3 25.5 22.6
Total assets 21.6 36.5 36.9 38.2 40.4 44.1
Payables 0.6 0.9 1.2 1.3 1.4
Senior debt 11.6 22.6 22.6 20.8 17.0 13.2
Total liabilities 11.6 23.3 23.5 22.0 18.3 14.6
Paid-in capital 10.0 15.0 15.0 15.0 15.0 15.0
Retained earnings -1.8 -1.6 1.2 7.1 14.5
Total equity 10.0 13.2 13.4 16.2 22.1 29.5
Liabilities + equity 21.6 36.5 36.9 38.2 40.4 44.1

13.5 Projected cash-flow statement

Table 17. Summary cash-flow statement, Years
3–10 (R billion).

R bn Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10
Operating cash flow -1.4 0.8 3.4 4.1 4.4 4.8 5.2
Investing (capex) -14.0 -13.0
Financing 16.0 16.0 -1.9 -1.9 -1.9 -1.9 -1.9
Net cash flow 2.0 1.6 0.8 1.5 2.2 2.6 2.9 3.3
Closing cash 2.0 3.6 4.4 5.9 8.1 10.7 13.6 16.9
Figure 10
Figure 10 — Closing cash balance — liquidity remains positive throughout construction and ramp.

13.5.1 Working-capital build

Working capital is modelled on 45 days of receivables, 50 days of
inventory and 40 days of payables. The investment in net working capital
builds as the plant ramps and stabilises at full output — a cash use
that the funding plan explicitly provides for.

Table 18. Net working-capital investment by year
(R billion).

R bn Y4 Y5 Y6 Y7 Y8 Y9 Y10
Net working capital 1.0 1.8 2.7 2.8 2.9 3.0 3.2
Annual WC investment 1.0 0.8 0.9 0.1 0.1 0.1 0.1

13.5.2 Monthly cash flow — first production year (Year 4)

Lenders require visibility of intra-year liquidity during
commissioning. The table and chart below set out the monthly operating
cash profile of the first production year, as output ramps from initial
commissioning toward the 40% annual average. Operating cash turns
positive as throughput rises, and the funding plan carries sufficient
reserves to bridge the early commissioning months.

Table 19. Year-4 monthly operating cash flow (R
million).

R m M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
Revenue 0 72 144 288 433 577 721 865 938 1010 1082 1082
Operating cost 235 271 308 381 416 489 562 635 671 707 744 744
Net operating cash -350 -314 -278 -207 -98 -26 45 116 152 188 223 223
Cumulative 1650 1337 1058 852 754 727 772 889 1041 1228 1452 1675
Figure 11
Figure 11 — Monthly operating cash flow through the first production year, with cumulative operating cash.

13.6 Debt service and cover

Senior debt is drawn during construction, carries an interest-only
grace period through commissioning and ramp (Years 4–5), and amortises
on a level-principal basis from Year 6. The debt-service cover ratio
(DSCR) strengthens steadily as the plant reaches nameplate, comfortably
clearing the 1.30x covenant floor from first repayment.

Figure 12
Figure 12 — Senior-debt balance profile, showing the interest-only grace period and amortisation from Year 6.
Figure 13
Figure 13 — Debt-service cover ratio versus the 1.30x covenant floor — strengthening to 1.91x by Year 10.

13.7 Key ratios

Table 20. Selected financial ratios.

Ratio Y4 Y5 Y6 Y7 Y8 Y9 Y10
EBITDA margin 14% 33% 38% 38% 38% 38% 38%
DSCR 1.31x 1.33x 1.50x 1.62x 1.75x 1.91x
Net debt / EBITDA 18.7x 4.2x 2.0x 1.4x 0.8x 0.2x -0.4x

13.8 Break-even analysis

On the full-production cost base — including fixed production cost,
overhead, depreciation and interest — the Project breaks even at
approximately 66% of nameplate capacity. Because the plant reaches 70%
utilisation in Year 5 and 100% in Year 6, it operates above break-even
from its second full year of production, providing a meaningful margin
of safety.

Figure 14
Figure 14 — Break-even analysis: revenue overtakes total cost (including financing and depreciation) at ~66% utilisation.
Figure 15
Figure 15 — Allocation of every rand of Year-6 revenue across cost, financing, tax and net profit.

13.9 Sensitivity analysis

The Project IRR is most sensitive to selling price, then to capital
cost and operating cost, and least to volume within the tested range.
The tornado below isolates the impact of a single-variable move from the
base case, holding all else constant.

Figure 16
Figure 16 — Single-variable sensitivity of project IRR (base case 22%).

13.10 Scenario analysis

Three integrated scenarios stress multiple variables together. The
downside combines a 10% price fall, 8% cost increase, a 10% slower ramp
and 10% capex overrun; the severe scenario layers a 20% price fall, 15%
cost increase, 20% slower ramp and 20% capex overrun. The base case
remains robustly value-accretive, the downside remains above the cost of
debt, and only the severe (low-probability) conjunction erodes value —
underscoring the importance of the equity cushion and contracted
offtake.

Table 21. Three-scenario analysis of project
returns.

Scenario Project IRR NPV @ 14.5%
Base 22.1% R10.92bn
Downside 11.2% R-4.31bn
Severe -0.7% R-17.43bn
Figure 17
Figure 17 — Project IRR and NPV across base, downside and severe scenarios (dashed line: WACC).

13.11 Valuation

Comparable global fertiliser and industrial-chemical businesses
typically trade at 7x–10x EBITDA. Applying this range to mature Year-6
EBITDA of R7.36bn implies an enterprise value of approximately R51.5bn
(low), R62.6bn (base) and R73.6bn (high). A successful migration toward
export-scale ammonia and hydrogen production could support a materially
higher strategic valuation over the longer term.

Figure 18
Figure 18 — Enterprise-value range on Year-6 EBITDA at 7.0x–10.0x (base case 8.5x).

13.12 Returns summary

Table 22. Headline return metrics (base
case).

Metric Value
Project IRR (unlevered, with terminal value) 22.3%
Project NPV @ 14.5% R11.17bn
Equity IRR (levered, with terminal value) 32.9%
Payback from first production 6.4 years
Break-even utilisation 66%
Minimum operating DSCR 1.31x (Year 5)
Enterprise value at exit (8.0x Year-10 EBITDA) R68.5bn

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of GreenH2 Fertiliser Holdings (Pty) Ltd.