Kalahari Grid Energy — Implementation Roadmap

The phased implementation roadmap, the bid-window and financial-close milestones and the build-out to 5 GW by 2032 underpinning Kalahari Grid.

Kalahari Grid Energy Business PlanSection 9 › Implementation Roadmap

Section 9 · Business Plan

Implementation Roadmap

The phased implementation roadmap, the bid-window and financial-close milestones and the build-out to 5 GW by 2032 underpinning Kalahari Grid.

The programme runs over roughly eight years (2026–2034), phased
around grid access and financial close rather than a fixed calendar.
Critical-path items are grid applications and connection agreements
(which gate everything), Phase 1 financial close, and the 24-month
EPC-to-COD cycle for each tranche. Regional (SADC) expansion and the
infrastructure-fund exit sit in the later years.

Figure 20
Figure 20 — 8-year 5 GW build-out Gantt

9.1 Phase milestones and dependencies

Milestone Target Depends on Gate
Platform & development team 2026 Sponsor capital; key hires Holdco ready
Grid applications & CELs 2026–2028 NTCSA process; site control Connection capacity
Phase 1 financial close (1.5 GW) 2027–2028 Grid; PPAs; equity + debt committed First close
Phase 1 COD (first revenue) 2029–2030 24-month EPC; grid connection Operating revenue
Phase 2 financial close (2.0 GW) 2029–2030 Phase 1 delivery; grid corridors Scale gate
Phase 2 COD 2031–2032 EPC delivery Revenue ramp
Phase 3 (regional, 1.5 GW) 2030–2032 SADC frameworks; regional grid Regional entry
Full 5 GW operational 2033 All tranches at COD Steady state
Refinance / infra-fund exit 2033–2034 Operating track record Exit optionality

9.2 Programme governance and close discipline

Execution risk concentrates in grid access and financial-close
velocity. The Company runs the programme under formal governance: a
board investment committee approving each SPV at financial close;
milestone-based equity and debt drawdowns against grid, PPA and
construction certification; and a hard rule that no tranche advances to
construction without a signed PPA and connection agreement in hand.

  • Grid before capital. No equity is committed to a
    project without secured connection capacity — the discipline that
    prevents stranded assets in a grid-constrained market.
  • Offtake before scale. Premium corporate PPAs are
    originated in parallel with REIPPPP bids to lift the blended tariff
    toward the bankable threshold before large equity is deployed.
  • Ring-fence the risk. Each SPV carries its own
    non-recourse debt and completion support, protecting the holdco and
    other projects from any single project’s difficulties.

9.3 Detailed workstream plan (Phase 1)

Phase 1 (1.5 GW) is the proof point that de-risks the platform. The
workstream plan below sequences the actions that must complete before
first financial close and first commercial operation.

Workstream Key actions Owner Timing
Grid CELs, budget quotes, connection agreements for Phase 1 sites Grid manager 2026–2027
Land Options and leases over grid-adjacent sites Development 2026–2027
Permitting Environmental authorisation, water use, land use Legal/env 2026–2028
Offtake REIPPPP bids (BW8+) and 2–3 anchor corporate PPAs Development 2026–2028
Financing Debt term sheets, equity commitments, DSRA Project finance 2027–2028
EPC Tender and award fixed-price turnkey contracts Engineering 2027–2028
Construction Build 1.5 GW to COD within 24 months Engineering 2028–2030
Operations O&M mobilisation, SCADA, PPA billing Asset mgmt 2029–2030

Successful Phase 1 delivery establishes the operating track record,
grid relationships and financing precedent that make Phases 2 and 3
materially lower-risk — the compounding advantage of the scale-first,
grid-corridor model.

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Kalahari Grid Energy (Pty) Ltd.