Red Rock Meats — Implementation Roadmap

The implementation plan follows a structured phased approach from company formation through to full commercial operations and export market entry:

Red Rock Meats (Pty) Ltd Business PlanSection 12 › Implementation Roadmap

Section 12 · Business Plan

Implementation Roadmap

The implementation plan follows a structured phased approach from company formation through to full commercial operations and export market entry:

12.1 Project Timeline

The implementation plan follows a structured phased approach from company formation through to full commercial operations and export market entry:

Phase 1: Foundation (Q1–Q2 2026)

  • Company registration and legal formation

  • Investor capital raise and debt financing finalisation

  • Land acquisition and environmental impact assessment

  • Architectural and engineering design finalisation

  • Key executive recruitment completion

Phase 2: Build (Q3–Q4 2026)

  • Facility construction and civil works

  • Equipment procurement and installation

  • Staff recruitment and training programme commencement

  • HACCP system development and documentation

  • Supplier contract finalisation

Phase 3: Launch (Q4 2026 – Q1 2027)

  • Trial production runs and quality validation

  • HACCP certification audit

  • Brand launch and initial customer onboarding

  • Full commercial production commencement (Q1 2027)

Phase 4: Scale (Q2 2027 – Q4 2028)

  • Capacity ramp-up to 12,000+ tonnes per annum

  • FSSC 22000 certification

  • Export market certification and first shipments

  • Value-added product line expansion

  • Second shift introduction

12.2 Implementation Gantt Chart

Project Timeline: Q1 2026 – Q2 2028

Activity / Phase Q1 26 Q2 26 Q3 26 Q4 26 Q1 27 Q2 27 Q3 27 Q4 27 Q1 28 Q2 28
Company Registration & Legal
Financing & Capital Raise
Land Acquisition & Permits
Facility Design & Construction
Equipment Procurement
Staff Recruitment & Training
HACCP & Certification
Trial Production Runs
Marketing & Brand Launch
Commercial Production
Export Market Entry

12.3 Key Milestones

Milestone Target Date Success Criteria Dependencies
Company Registration Q1 2026 CIPC registration complete; SARS registrations active Shareholder agreement signed
Financing Closed Q2 2026 ZAR 75M committed; term sheets executed Investor due diligence complete
Construction Complete Q4 2026 Facility handed over; occupancy certificate issued Permits; contractor performance
Equipment Installed Q4 2026 All lines commissioned and tested Import logistics; installation crew
HACCP Certified Q4 2026 Certification issued by accredited body QA system; trial production
Commercial Launch Q1 2027 First customer shipments; revenue commenced All certifications in place
Breakeven Q3 2029 Monthly EBITDA positive Revenue ramp; cost management
Export First Shipment Q3 2027 EU/SADC-compliant product exported Export certification
FSSC 22000 Certified Q2 2027 Certification achieved 12 months operational track record