Verdant Bites Co. — Implementation Plan & Timeline

The implementation plan has been structured across four key phases, with clear milestones and accountability at each stage:

Verdant Bites Co. (Pty) Ltd Business PlanSection 11 › Implementation Plan & Timeline

Section 11 · Business Plan

Implementation Plan & Timeline

The implementation plan has been structured across four key phases, with clear milestones and accountability at each stage:

11.1 18-Month Implementation Gantt Chart

The implementation plan has been structured across four key phases, with clear milestones and accountability at each stage:

Figure
Gantt Chart — visualised from the accompanying data.

11.2 Key Milestones

Month Milestone Accountable
M1–M2 Company registration, CIPC compliance, B-BBEE verification CEO / Legal Counsel
M1–M3 Investor close, funds received, bank accounts established CFO / Investor Director
M2–M4 Site selection, lease negotiation, heads of terms signed COO
M3–M5 Architectural design, municipal permits, health & safety approvals COO / Architect
M5–M9 Leasehold improvements, store fitout, equipment installation COO / Contractor
M7–M10 Staff recruitment, training programme, dry-run operations Store Manager / HR
M9–M11 Pre-launch marketing campaign, influencer activations Marketing Manager
M11 Soft launch with invited guests and select corporate clients CEO / COO
M12 Grand opening — full public launch Full Team
M13–M18 Post-launch optimisation, Phase 2 planning initiated CEO / COO