Vitalis Group SA — Implementation Roadmap & Gantt Plan
The phased implementation roadmap and Gantt plan, with key milestones from licensing and platform build to launch and scale.
Section 14 · Business Plan
Implementation Roadmap & Gantt Plan
The phased implementation roadmap and Gantt plan, with key milestones from licensing and platform build to launch and scale.
14.1 Five-Phase Implementation Plan
The Vitalis implementation plan is organised into five sequential and
partially-overlapping phases, executed over 60 months from financial
close. The phases are: (1) Foundation; (2) Platform Build; (3) Market
Launch; (4) Scale and Optimise; (5) Profitability and Exit
Readiness.
14.2 Phase 1: Foundation (Months 0 – 6)
Foundation activities establish the legal, regulatory and people
infrastructure of the Company.
- Company registration; capital injection; opening balance sheet
established - Pre-application engagement with PA and FSCA; formal licence
applications filed by M+3 - Reinsurance treaties signed with three Tier-1 reinsurers (quota
share, catastrophe) - Hiring of CEO, ExCo and senior actuarial / underwriting team (40
hires) - Premises secured in Sandton, Cape Town and Durban
- Selection of core technology vendors and signed master service
agreements
14.3 Phase 2: Platform Build (Months 4 – 13)
Platform build operates in parallel with the closing months of Phase
1 to compress the time to launch. Build activities are split across nine
engineering streams operating in agile cadence.
- Policy administration and claims system configured and
customised - Underwriting engine and pricing models developed; actuarial
review and calibration - Wellness platform built (proprietary, integrating wearable
APIs) - Mobile application and member portal developed and
tested - Broker portal and embedded-insurance API gateway
delivered - Integration with payments, KYC, credit-bureau and reinsurance
partners - Independent third-party security and conduct testing
14.4 Phase 3: Market Launch (Months 12 – 20)
Phase 3 takes the Company from regulatory approval through to a
full-scale national launch.
- Soft pilot launch in Gauteng (M12 – M14) with internal and
limited-friends-and-family customers - Full Gauteng launch (M15); Western Cape and KZN added
M17–M18 - Broker network activation: 80 Platinum / Gold brokers contracted
in Year 1 - National rollout across all nine provinces (M19–M20)
- Banking proposition launched (M18) under Tier 2 licence
14.5 Phase 4: Scale and Optimise (Months 20 – 36)
The Company accelerates customer acquisition and product cross-sell
while maintaining underwriting discipline.
- Cross-sell engine activated; in-app product recommendations
live - Investment platform launched (M24); HNW tied-advisory force built
(M28) - Regional expansion: first SADC market (Botswana) entered M30 via
JV - EBITDA breakeven achieved by M32 (base case)
14.6 Phase 5: Profitability and Exit Readiness (Months 32 – 60)
The Company achieves sustainable profitability and prepares for
liquidity event.
- Sustained EBITDA-positive operations; cumulative EBITDA above
R1.2 Bn by M60 - Series B capital raise (M36): R600M to fund SADC and product
acceleration - Internal model development for SAM (M40 onwards)
- JSE IPO preparation work commences M48; bookrunner appointment
M54 - IPO targeted Year 7 (M72–M84) — see Section 22
14.7 Critical Path and Dependencies
The critical path is dominated by regulatory licensing. A 90-day
delay in primary licence issuance translates to a 120-day delay in
EBITDA breakeven, with a financial-impact equivalent of ~R85M additional
cumulative cash burn. Mitigating actions include early pre-application
engagement, fallback structures using fronted reinsurance, and a
Lloyds-cell launch option for a subset of products.
| Critical Milestone | Target Month | Predecessor | Latest Acceptable |
|---|---|---|---|
| Primary licence issuance | M+6 | Filing complete | M+9 |
| Reinsurance treaty execution | M+7 | Licence in principle | M+10 |
| Technology platform UAT signoff | M+11 | Build complete | M+13 |
| Pilot launch (Gauteng) | M+13 | Platform + licence | M+15 |
| National launch | M+20 | Pilot results positive | M+22 |
| EBITDA breakeven | M+32 | Customer growth on plan | M+38 |
| Series B raise | M+36 | Audited Yr 3 results | M+42 |