Cryostead Logistics — Implementation Plan & Gantt Chart

The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction…

Cryostead Logistics (Pty) Ltd Business PlanSection 11 › Implementation Plan & Gantt Chart

Section 11 · Business Plan

Implementation Plan & Gantt Chart

The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction…

The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction and commissioning durations for a facility of this scale.

Figure
Gantt — visualised from the accompanying data.

11.1 Key Milestones

Month Milestone Responsible Status Gate
M1–M4 Site acquisition, EIA approval, building permits obtained CEO / Legal Board Approval
M5–M10 Foundation and structural construction completed Project Manager Engineer Sign-Off
M10–M16 Refrigeration and electrical systems installed and tested COO / Engineers Commissioning Report
M14–M18 WMS, IoT systems integrated; staff recruited and trained COO / IT UAT Completion
M18–M20 Regulatory approvals obtained; HACCP certification QA Manager Certificate Issued
M20–M22 Soft launch with anchor tenants; operational fine-tuning COO / Sales Client SLA Sign-Off
M22+ Full commercial operations commence All Revenue Recognition