Cryostead Logistics — Implementation Plan & Gantt Chart
The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction…
Section 11 · Business Plan
Implementation Plan & Gantt Chart
The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction…
The implementation plan spans 24 months from project initiation to full commercial operations, with a further 12 months for Phase 2 automation and expansion initiatives. The timeline has been developed in consultation with specialist cold chain engineering firms and reflects realistic construction and commissioning durations for a facility of this scale.
11.1 Key Milestones
| Month | Milestone | Responsible | Status Gate |
|---|---|---|---|
| M1–M4 | Site acquisition, EIA approval, building permits obtained | CEO / Legal | Board Approval |
| M5–M10 | Foundation and structural construction completed | Project Manager | Engineer Sign-Off |
| M10–M16 | Refrigeration and electrical systems installed and tested | COO / Engineers | Commissioning Report |
| M14–M18 | WMS, IoT systems integrated; staff recruited and trained | COO / IT | UAT Completion |
| M18–M20 | Regulatory approvals obtained; HACCP certification | QA Manager | Certificate Issued |
| M20–M22 | Soft launch with anchor tenants; operational fine-tuning | COO / Sales | Client SLA Sign-Off |
| M22+ | Full commercial operations commence | All | Revenue Recognition |