Africa Green Energy Holdings — Financial Plan – Assumptions
The key financial assumptions underpinning the model — generation yields, tariffs and escalation, cost structure, capital structure, tax and the macroeconomic inputs.
Section 13 · Business Plan
Financial Plan – Assumptions
The key financial assumptions underpinning the model — generation yields, tariffs and escalation, cost structure, capital structure, tax and the macroeconomic inputs.
This section sets out the integrated financial model assumptions that
underpin AGEH’s projected Profit & Loss, Balance Sheet and Cash Flow
statements presented in Sections 14, 15 and 16. The model is built
bottom-up at the project SPV level and consolidated to holding company
level, in nominal Rand terms, over a 12-year horizon (FY2027 development
through FY2036 steady-state operations). The base case reflects
management’s central case; sensitivity outputs are presented in Section
18.
13.1 Macroeconomic Assumptions
Macroeconomic assumptions are anchored to the South African Reserve
Bank (SARB) Monetary Policy Committee projections and National
Treasury’s 2026 Medium-Term Budget Policy Statement (MTBPS). Headline
CPI is modelled at 4.5% over the projection horizon, consistent with the
SARB’s 3-6% target band and the recent revision toward a 3% point
target. The ZAR/USD rate of R18.50 reflects the trailing 12-month
average; sensitivity is tested at R16.50 (revaluation) and R21.00
(depreciation). The real risk-free rate is anchored to South African
10-year inflation-linked bond yields.
| Macroeconomic Variable | FY2027 | FY2028 | FY2029 | FY2030 | FY2031-36 |
|---|---|---|---|---|---|
| South African CPI (%) | 4.8% | 4.6% | 4.5% | 4.5% | 4.5% |
| US CPI (%) | 2.5% | 2.3% | 2.2% | 2.2% | 2.2% |
| ZAR/USD (period average) | 18.50 | 18.95 | 19.40 | 19.85 | +2.3% p.a. |
| SARB repo rate (%) | 7.00% | 6.75% | 6.50% | 6.50% | 6.50% |
| 10-year SA government bond yield (%) | 9.80% | 9.50% | 9.25% | 9.00% | 9.00% |
| NERSA-approved Eskom tariff increase (%) | 12.7% | 5.4% | 6.2% | 6.0% | 5.5% |
| GDP growth (%) | 1.8% | 2.0% | 2.2% | 2.3% | 2.3% |
Table 13.1 — Macroeconomic Assumptions (Sources: SARB, National
Treasury, NERSA)
13.2 Revenue Assumptions
Revenue is generated from three distinct streams: REIPPPP Bid Window
8 PPAs (solar PV), corporate PPAs (wind), and BESIPPPP / energy-trading
revenues (battery storage). Each stream is modelled with asset-specific
yield, degradation and indexation parameters.
Solar PV (300 MW)
| Parameter | Assumption | Source / Rationale |
|---|---|---|
| Installed capacity (MWac) | 300 | REIPPPP BW8 award allocation |
| P50 capacity factor (Year 1) | 28.5% | Solargis irradiance study, Northern Cape sites |
| P90 capacity factor (Year 1) | 26.8% | Used for debt sizing per IFC PR2.7 |
| Annual energy yield, Year 1 (GWh) | 748.7 | P50 × 8,760 hours × 300 MW × availability |
| System availability (post-COD) | 98.5% | Tier-1 inverter & tracker contracts |
| Module degradation (Year 1) | 2.0% | Standard Tier-1 LID + module warranty |
| Module degradation (Year 2 onward) | 0.45% p.a. | Linear, IFC standard methodology |
| Base tariff (Apr 2025 ZAR) | R0.512/kWh | REIPPPP BW7 weighted average |
| Tariff indexation | 100% CPI | Standard REIPPPP PPA template |
| PPA tenor | 20 years | Eskom as offtaker, NTCSA wheeling |
Table 13.2 — Solar PV Operating Assumptions
Wind (150 MW)
| Parameter | Assumption | Source / Rationale |
|---|---|---|
| Installed capacity (MW) | 150 | Eastern Cape / Western Cape sites |
| P50 capacity factor (Year 1) | 42.0% | Independent wind resource assessment, 24-month met-mast |
| P90 capacity factor (Year 1) | 39.5% | Used for debt sizing |
| Annual energy yield, Year 1 (GWh) | 551.9 | P50 × 8,760 × 150 MW |
| System availability (post-COD) | 97.0% | 5.6 MW Tier-1 turbine class, 15-yr full-service O&M |
| Turbine degradation | 0.30% p.a. | Manufacturer-warranted curve |
| Tariff – corporate PPA base (Apr 2025 ZAR) | R0.720/kWh | 85% of weighted Eskom MYPD6 tariff |
| Corporate PPA indexation | CPI + 0.5% | Bilateral negotiation; reflects T&D cost passthrough |
| Corporate PPA tenor | 15 years | Anchor offtaker contracts |
| Floor / merchant exposure | 20% | Sold via NTCSA wheeling at market clearing price |
Table 13.3 — Wind Operating Assumptions
Battery Energy Storage (100 MW / 400 MWh)
| Parameter | Assumption | Source / Rationale |
|---|---|---|
| Power rating (MW) | 100 | BESIPPPP / ancillary services tender |
| Energy rating (MWh) | 400 | 4-hour duration for capacity market |
| Round-trip efficiency | 87% | Tier-1 LFP chemistry |
| Annual cycles | 365 | 1 cycle/day arbitrage + ancillary services |
| Capacity payment (R/MW/month) | R1,250,000 | Indexed at CPI |
| Energy throughput revenue (R/MWh) | R580 | Net of charging cost spread |
| Augmentation reserve (% of CAPEX) | 8% | Year-7 and Year-12 cell replacement |
| Degradation | 2.5% Yr1, 1.0% Yr2+ | Cycle-life curve, 70% EOL at Year 15 |
| PPA tenor | 15 years | BESIPPPP standard |
Table 13.4 — Battery Storage Operating Assumptions
13.3 Operating Cost Assumptions
Operating costs are modelled bottom-up per asset class and indexed at
South African CPI unless otherwise stated. The model carries a 10%
management reserve on aggregate OPEX for the first three operating years
to absorb early-life teething costs, declining to 5% thereafter.
| Cost Category | Solar (R/kW/yr) | Wind (R/kW/yr) | BESS (R/kW/yr) | Indexation |
|---|---|---|---|---|
| O&M – fixed (full-service contract) | 180 | 420 | 240 | CPI |
| O&M – variable | 45 | 85 | 60 | CPI |
| Land lease / servitudes | 95 | 140 | 35 | CPI + 1.0% |
| Insurance (property, BI, liability) | 85 | 120 | 75 | CPI |
| Asset management fee (IRAMC) | 65 | 65 | 65 | CPI |
| Grid use-of-system & wheeling | 180 | 180 | 180 | NERSA-approved |
| SHEQ, security, community | 55 | 70 | 30 | CPI |
| G&A allocation | 40 | 40 | 40 | CPI |
| Total OPEX (Year 1, ZAR) | 745 | 1,120 | 725 |
Table 13.5 — Operating Cost Assumptions by Asset Class
13.4 Capital Cost & Funding Assumptions
Total project capital cost is R8,850 million inclusive of development
costs, hard EPC scope, owner’s costs, IDC and a contingency reserve. The
CAPEX build-up reflects competitive Tier-1 EPC quotations received
during the December 2025 tender process, benchmarked against REIPPPP BW7
awarded tariffs and IFC’s emerging-markets cost database.
| CAPEX Component | Solar (R m) | Wind (R m) | BESS (R m) | Total (R m) | % of Total |
|---|---|---|---|---|---|
| EPC – mechanical & electrical | 3,250 | 2,050 | 1,420 | 6,720 | 75.9% |
| Owner’s plant (substation, BoP) | 380 | 240 | 85 | 705 | 8.0% |
| Grid connection & transmission | 210 | 140 | 60 | 410 | 4.6% |
| Development costs (capitalised) | 180 | 110 | 60 | 350 | 4.0% |
| Land acquisition & servitudes | 45 | 35 | 10 | 90 | 1.0% |
| Insurance during construction | 35 | 25 | 15 | 75 | 0.8% |
| Financing fees & legal | 65 | 40 | 30 | 135 | 1.5% |
| Interest during construction (IDC) | 85 | 55 | 40 | 180 | 2.0% |
| Contingency (3% net) | 100 | 55 | 30 | 185 | 2.1% |
| Total CAPEX | 4,350 | 2,750 | 1,750 | 8,850 | 100.0% |
Table 13.6 — Total Capital Expenditure Build-Up
13.5 Capital Structure & Debt Terms
AGEH’s senior secured debt facilities are structured on a
non-recourse project-finance basis with separate SPVs for each asset
class. Headline terms reflect indicative term sheets received from the
IFC, three DFI co-lenders and two South African commercial banks, all of
which have completed credit committee preliminary approval.
| Tranche | Provider | Amount (R m) | Tenor | Margin | Repayment |
|---|---|---|---|---|---|
| Sponsor Equity | AGEH sponsors + BEE | 1,500 | Permanent | n/a | Residual |
| IFC A-Loan (senior secured) | IFC | 3,000 | 18 yrs | JIBAR + 295 bps | Sculpted, semi-annual |
| DFI B-Loan / Co-Financing | AfDB, DBSA, KfW | 2,000 | 18 yrs | JIBAR + 285 bps | Sculpted, pari passu |
| Commercial Bank Facility | ABSA, Standard Bank | 2,000 | 15 yrs | JIBAR + 325 bps | Mortgage-style |
| IFC Climate Finance / Blended | IFC Canada CBFL | 350 | 20 yrs | JIBAR + 195 bps | Bullet at Year 20 |
| Total Capitalisation | 8,850 |
Table 13.7 — Capital Structure & Indicative Debt
Terms
13.6 Tax & Depreciation
The financial model applies the South African corporate income tax
rate of 27%. Section 12B of the Income Tax Act permits 100% accelerated
depreciation for renewable energy assets brought into use after 1 March
2023, materially enhancing early-year tax shields. AGEH’s structure
routes asset ownership through SPVs to maximise utilisation of these
allowances:
- Solar PV & Wind generation assets: 100% Section 12B allowance
in Year 1 of commercial operation, creating substantial assessed-loss
carryforwards that shelter taxable income through Year 6-7. - BESS assets: 50/30/20 accelerated allowance under Section 12B for
storage assets, with full deduction within three years. - Civil works & substation infrastructure: Straight-line
25-year depreciation per IFRS, separately tracked from tax
depreciation. - Capitalised development costs: Amortised over PPA tenor for
accounting purposes; deductible in year of incurral for tax
purposes. - Carbon tax: Renewable assets benefit from full carbon credit
offset eligibility under the Carbon Tax Act (Act 15 of 2019);
incremental revenue not modelled in base case.
13.7 Working Capital & Reserves
The model assumes 60 days of revenue receivable (Eskom historically
pays within 35 days; conservatism reflects corporate counterparties) and
30 days of OPEX payables. Three dedicated reserve accounts are funded
from operating cash flow per lender requirements:
- Debt Service Reserve Account (DSRA): 6 months of forward debt
service, funded at financial close from drawdowns. - Maintenance Reserve Account (MRA): Progressively funded over
Years 1-5 to a target of R125 million by Year 6, sized against the
major-overhaul schedule. - BESS Augmentation Reserve: R15 million per annum from Year 1,
sized to fund Year-7 and Year-12 cell replacement programmes.
13.8 Distribution Policy
Dividend distributions to shareholders are subject to the following
lender-mandated lockup tests: (i) Historic 12-month DSCR ≥ 1.20x; (ii)
Forward-looking 12-month DSCR ≥ 1.20x; (iii) All reserve accounts fully
funded; (iv) No event of default subsisting. Subject to these tests,
100% of distributable cash is paid out semi-annually. Lock-up cure
mechanisms include an equity cure provision and a 12-month standstill
before enforcement.
Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Africa Green Energy Holdings (Pty) Ltd.