Africa Green Energy Holdings — Financial Plan – Assumptions

The key financial assumptions underpinning the model — generation yields, tariffs and escalation, cost structure, capital structure, tax and the macroeconomic inputs.

Africa Green Energy Holdings Business PlanSection 13 › Financial Plan – Assumptions

Section 13 · Business Plan

Financial Plan – Assumptions

The key financial assumptions underpinning the model — generation yields, tariffs and escalation, cost structure, capital structure, tax and the macroeconomic inputs.

This section sets out the integrated financial model assumptions that
underpin AGEH’s projected Profit & Loss, Balance Sheet and Cash Flow
statements presented in Sections 14, 15 and 16. The model is built
bottom-up at the project SPV level and consolidated to holding company
level, in nominal Rand terms, over a 12-year horizon (FY2027 development
through FY2036 steady-state operations). The base case reflects
management’s central case; sensitivity outputs are presented in Section
18.

13.1 Macroeconomic Assumptions

Macroeconomic assumptions are anchored to the South African Reserve
Bank (SARB) Monetary Policy Committee projections and National
Treasury’s 2026 Medium-Term Budget Policy Statement (MTBPS). Headline
CPI is modelled at 4.5% over the projection horizon, consistent with the
SARB’s 3-6% target band and the recent revision toward a 3% point
target. The ZAR/USD rate of R18.50 reflects the trailing 12-month
average; sensitivity is tested at R16.50 (revaluation) and R21.00
(depreciation). The real risk-free rate is anchored to South African
10-year inflation-linked bond yields.

Macroeconomic Variable FY2027 FY2028 FY2029 FY2030 FY2031-36
South African CPI (%) 4.8% 4.6% 4.5% 4.5% 4.5%
US CPI (%) 2.5% 2.3% 2.2% 2.2% 2.2%
ZAR/USD (period average) 18.50 18.95 19.40 19.85 +2.3% p.a.
SARB repo rate (%) 7.00% 6.75% 6.50% 6.50% 6.50%
10-year SA government bond yield (%) 9.80% 9.50% 9.25% 9.00% 9.00%
NERSA-approved Eskom tariff increase (%) 12.7% 5.4% 6.2% 6.0% 5.5%
GDP growth (%) 1.8% 2.0% 2.2% 2.3% 2.3%

Table 13.1 — Macroeconomic Assumptions (Sources: SARB, National
Treasury, NERSA)

13.2 Revenue Assumptions

Revenue is generated from three distinct streams: REIPPPP Bid Window
8 PPAs (solar PV), corporate PPAs (wind), and BESIPPPP / energy-trading
revenues (battery storage). Each stream is modelled with asset-specific
yield, degradation and indexation parameters.

Solar PV (300 MW)

Parameter Assumption Source / Rationale
Installed capacity (MWac) 300 REIPPPP BW8 award allocation
P50 capacity factor (Year 1) 28.5% Solargis irradiance study, Northern Cape sites
P90 capacity factor (Year 1) 26.8% Used for debt sizing per IFC PR2.7
Annual energy yield, Year 1 (GWh) 748.7 P50 × 8,760 hours × 300 MW × availability
System availability (post-COD) 98.5% Tier-1 inverter & tracker contracts
Module degradation (Year 1) 2.0% Standard Tier-1 LID + module warranty
Module degradation (Year 2 onward) 0.45% p.a. Linear, IFC standard methodology
Base tariff (Apr 2025 ZAR) R0.512/kWh REIPPPP BW7 weighted average
Tariff indexation 100% CPI Standard REIPPPP PPA template
PPA tenor 20 years Eskom as offtaker, NTCSA wheeling

Table 13.2 — Solar PV Operating Assumptions

Wind (150 MW)

Parameter Assumption Source / Rationale
Installed capacity (MW) 150 Eastern Cape / Western Cape sites
P50 capacity factor (Year 1) 42.0% Independent wind resource assessment, 24-month met-mast
P90 capacity factor (Year 1) 39.5% Used for debt sizing
Annual energy yield, Year 1 (GWh) 551.9 P50 × 8,760 × 150 MW
System availability (post-COD) 97.0% 5.6 MW Tier-1 turbine class, 15-yr full-service O&M
Turbine degradation 0.30% p.a. Manufacturer-warranted curve
Tariff – corporate PPA base (Apr 2025 ZAR) R0.720/kWh 85% of weighted Eskom MYPD6 tariff
Corporate PPA indexation CPI + 0.5% Bilateral negotiation; reflects T&D cost passthrough
Corporate PPA tenor 15 years Anchor offtaker contracts
Floor / merchant exposure 20% Sold via NTCSA wheeling at market clearing price

Table 13.3 — Wind Operating Assumptions

Battery Energy Storage (100 MW / 400 MWh)

Parameter Assumption Source / Rationale
Power rating (MW) 100 BESIPPPP / ancillary services tender
Energy rating (MWh) 400 4-hour duration for capacity market
Round-trip efficiency 87% Tier-1 LFP chemistry
Annual cycles 365 1 cycle/day arbitrage + ancillary services
Capacity payment (R/MW/month) R1,250,000 Indexed at CPI
Energy throughput revenue (R/MWh) R580 Net of charging cost spread
Augmentation reserve (% of CAPEX) 8% Year-7 and Year-12 cell replacement
Degradation 2.5% Yr1, 1.0% Yr2+ Cycle-life curve, 70% EOL at Year 15
PPA tenor 15 years BESIPPPP standard

Table 13.4 — Battery Storage Operating Assumptions

13.3 Operating Cost Assumptions

Operating costs are modelled bottom-up per asset class and indexed at
South African CPI unless otherwise stated. The model carries a 10%
management reserve on aggregate OPEX for the first three operating years
to absorb early-life teething costs, declining to 5% thereafter.

Cost Category Solar (R/kW/yr) Wind (R/kW/yr) BESS (R/kW/yr) Indexation
O&M – fixed (full-service contract) 180 420 240 CPI
O&M – variable 45 85 60 CPI
Land lease / servitudes 95 140 35 CPI + 1.0%
Insurance (property, BI, liability) 85 120 75 CPI
Asset management fee (IRAMC) 65 65 65 CPI
Grid use-of-system & wheeling 180 180 180 NERSA-approved
SHEQ, security, community 55 70 30 CPI
G&A allocation 40 40 40 CPI
Total OPEX (Year 1, ZAR) 745 1,120 725

Table 13.5 — Operating Cost Assumptions by Asset Class

13.4 Capital Cost & Funding Assumptions

Total project capital cost is R8,850 million inclusive of development
costs, hard EPC scope, owner’s costs, IDC and a contingency reserve. The
CAPEX build-up reflects competitive Tier-1 EPC quotations received
during the December 2025 tender process, benchmarked against REIPPPP BW7
awarded tariffs and IFC’s emerging-markets cost database.

CAPEX Component Solar (R m) Wind (R m) BESS (R m) Total (R m) % of Total
EPC – mechanical & electrical 3,250 2,050 1,420 6,720 75.9%
Owner’s plant (substation, BoP) 380 240 85 705 8.0%
Grid connection & transmission 210 140 60 410 4.6%
Development costs (capitalised) 180 110 60 350 4.0%
Land acquisition & servitudes 45 35 10 90 1.0%
Insurance during construction 35 25 15 75 0.8%
Financing fees & legal 65 40 30 135 1.5%
Interest during construction (IDC) 85 55 40 180 2.0%
Contingency (3% net) 100 55 30 185 2.1%
Total CAPEX 4,350 2,750 1,750 8,850 100.0%

Table 13.6 — Total Capital Expenditure Build-Up

Figure 13.1
Figure 13.1 — Use of Proceeds Allocation

13.5 Capital Structure & Debt Terms

AGEH’s senior secured debt facilities are structured on a
non-recourse project-finance basis with separate SPVs for each asset
class. Headline terms reflect indicative term sheets received from the
IFC, three DFI co-lenders and two South African commercial banks, all of
which have completed credit committee preliminary approval.

Tranche Provider Amount (R m) Tenor Margin Repayment
Sponsor Equity AGEH sponsors + BEE 1,500 Permanent n/a Residual
IFC A-Loan (senior secured) IFC 3,000 18 yrs JIBAR + 295 bps Sculpted, semi-annual
DFI B-Loan / Co-Financing AfDB, DBSA, KfW 2,000 18 yrs JIBAR + 285 bps Sculpted, pari passu
Commercial Bank Facility ABSA, Standard Bank 2,000 15 yrs JIBAR + 325 bps Mortgage-style
IFC Climate Finance / Blended IFC Canada CBFL 350 20 yrs JIBAR + 195 bps Bullet at Year 20
Total Capitalisation 8,850

Table 13.7 — Capital Structure & Indicative Debt
Terms

Figure 13.2
Figure 13.2 — Capital Stack by Funding Source

13.6 Tax & Depreciation

The financial model applies the South African corporate income tax
rate of 27%. Section 12B of the Income Tax Act permits 100% accelerated
depreciation for renewable energy assets brought into use after 1 March
2023, materially enhancing early-year tax shields. AGEH’s structure
routes asset ownership through SPVs to maximise utilisation of these
allowances:

  • Solar PV & Wind generation assets: 100% Section 12B allowance
    in Year 1 of commercial operation, creating substantial assessed-loss
    carryforwards that shelter taxable income through Year 6-7.
  • BESS assets: 50/30/20 accelerated allowance under Section 12B for
    storage assets, with full deduction within three years.
  • Civil works & substation infrastructure: Straight-line
    25-year depreciation per IFRS, separately tracked from tax
    depreciation.
  • Capitalised development costs: Amortised over PPA tenor for
    accounting purposes; deductible in year of incurral for tax
    purposes.
  • Carbon tax: Renewable assets benefit from full carbon credit
    offset eligibility under the Carbon Tax Act (Act 15 of 2019);
    incremental revenue not modelled in base case.

13.7 Working Capital & Reserves

The model assumes 60 days of revenue receivable (Eskom historically
pays within 35 days; conservatism reflects corporate counterparties) and
30 days of OPEX payables. Three dedicated reserve accounts are funded
from operating cash flow per lender requirements:

  • Debt Service Reserve Account (DSRA): 6 months of forward debt
    service, funded at financial close from drawdowns.
  • Maintenance Reserve Account (MRA): Progressively funded over
    Years 1-5 to a target of R125 million by Year 6, sized against the
    major-overhaul schedule.
  • BESS Augmentation Reserve: R15 million per annum from Year 1,
    sized to fund Year-7 and Year-12 cell replacement programmes.

13.8 Distribution Policy

Dividend distributions to shareholders are subject to the following
lender-mandated lockup tests: (i) Historic 12-month DSCR ≥ 1.20x; (ii)
Forward-looking 12-month DSCR ≥ 1.20x; (iii) All reserve accounts fully
funded; (iv) No event of default subsisting. Subject to these tests,
100% of distributable cash is paid out semi-annually. Lock-up cure
mechanisms include an equity cure provision and a 12-month standstill
before enforcement.

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Africa Green Energy Holdings (Pty) Ltd.