AgriFeed Holdings — Implementation Roadmap & Gantt Chart
The phased implementation roadmap and Gantt chart, with key milestones from financial close and mill construction through commissioning to ramp-up and Phase 2.
Section 13 · Business Plan
Implementation Roadmap & Gantt Chart
The phased implementation roadmap and Gantt chart, with key milestones from financial close and mill construction through commissioning to ramp-up and Phase 2.
The implementation roadmap is structured in four sequential phases
over a 48-month horizon, from financial close (Month 0) through SADC
market entry (Month 48). The plan is engineered for early operating cash
generation: first commercial production is achieved in Month 19, with
full Phase 1 ramp-up by Month 33.
13.1 Phase 0 — Pre-development (Months 1–5)
- Capital raise close: senior debt, mezzanine, and equity all
signed by M3. - Site acquisition: complete the eMalahleni 12 Ha brownfield
purchase by M5; transfer registered. - Detailed engineering brief, OEM contracts (Bühler / Andritz)
signed. - Environmental Impact Assessment scoping report submitted to
DFFE.
13.2 Phase 1 — Engineering & Civils (Months 4–12)
- Detailed engineering: 100% issued-for-construction drawings by
M7. - All regulatory permits (Environmental Authorisation, Water Use
License, Air Emission License, Building Plans) approved by M8. - Civil works: site preparation, foundations, building shell
complete by M11. - Long-lead equipment manufactured and shipped (pellet press,
mixers) by M12.
13.3 Phase 2 — Plant Build & Fit-out (Months 11–18)
- Mill mechanical and electrical installation, pelleting line
erection. - Silo erection (8 raw-material × 500 t and 12 finished-product
silos). - ERP, MES, and laboratory systems implemented and
integrated. - Phased hiring: 60 mill staff trained on operational procedures by
M18.
13.4 Phase 3 — Commissioning & Launch (Months 18–33)
- Cold and hot commissioning: feed trials, FCR validation,
food-safety qualifications. - First commercial production and sale: M19.
- Customer onboarding: anchor Tier 1 contract activated; mid-market
sales force fully deployed. - Year 1 ramp: 35% utilisation by M27, 55% by M33.
13.5 Phase 4 — Expansion (Months 30–48)
- Phase 2 KZN site (Pietermaritzburg/Cato Ridge area) —
feasibility, EIA, civils start M30. - Phase 2 capital raise (~ZAR 200 m) finalised by M33.
- SADC entry: Zambia (Lusaka distribution hub) by M40; Zimbabwe and
Mozambique progressively. - Aquaculture pellet line option triggered if internal trials and
customer commitment crystallised by M36.
13.6 Critical Path & Dependencies
The principal critical-path items are: (i) regulatory approval of the
Environmental Authorisation under NEMA Listing Notice 2 (a slip of one
month results in a one-month slip in commissioning); (ii) lead time on
imported pelleting equipment (typically 36–42 weeks ex-works Europe);
and (iii) first commercial Tier 1 anchor contract execution conditional
on financial close. The schedule includes a 6-week float on the
equipment lead time and a 4-week float on regulatory approvals; both are
tracked weekly through the project director’s office.