Citriona Valley Farms — Implementation Timeline

The project implementation follows a structured 60-month development programme, divided into three distinct phases: Establishment (Months 1–18), Early Production (Months 19–36), and Full Commercial Operations (Months 37–60). The Gantt chart below provides a visual overview of key workstreams and milestones.

Citriona Valley Farms (Pty) Ltd Business PlanSection 11 › Implementation Timeline

Section 11 · Business Plan

Implementation Timeline

The project implementation follows a structured 60-month development programme, divided into three distinct phases: Establishment (Months 1–18), Early Production (Months 19–36), and Full Commercial Operations (Months 37–60). The Gantt chart below provides a visual overview of key workstreams and milestones.

The project implementation follows a structured 60-month development programme, divided into three distinct phases: Establishment (Months 1–18), Early Production (Months 19–36), and Full Commercial Operations (Months 37–60). The Gantt chart below provides a visual overview of key workstreams and milestones.

Figure
Gantt Chart — visualised from the accompanying data.

Figure 10: Implementation Gantt Chart – 60-Month Horizon

11.1 Phase 1: Establishment (Months 1–18)

This phase encompasses all foundational activities required to bring the farm to a state of operational readiness. Critical path activities include land transfer and registration, environmental impact assessment and water-use licence application, borehole drilling and irrigation installation, soil preparation and amendment, and phased tree planting (Phase 1: 55 hectares in months 6–12; Phase 2: 35 hectares in months 12–18).

11.2 Phase 2: Early Production (Months 19–36)

Young trees begin producing limited yields from approximately 24 months post-planting. This phase focuses on orchard management and canopy development, initial harvest and quality grading, export market registration and certification, brand development and marketing launch, and packhouse and cold chain partnership establishment.

11.3 Phase 3: Full Commercial Operations (Months 37–60)

Trees reach commercial bearing from Year 4, with production scaling to target levels by Year 5. Key activities in this phase include production optimisation and yield maximisation, full export programme execution, organic certification for the designated 15-hectare block, financial performance stabilisation and potential debt refinancing, and development of expansion plans for Phase 2 growth.

11.4 Key Milestones

Timeline Milestone Deliverable
Month 1 Financial Close & Land Transfer Title deed registered
Month 4 Water Use Licence Approved DWAS approval letter
Month 8 Irrigation System Commissioned System operational
Month 12 Phase 1 Planting Complete (55ha) 55ha planted & certified
Month 18 Phase 2 Planting Complete (90ha total) 90ha planted & certified
Month 24 First Limited Harvest ~450 tons harvested
Month 30 Export Certification Achieved GlobalG.A.P. certified
Month 42 Commercial Production Begins 3,600+ tons/annum
Month 54 Full Production Achieved 4,500 tons/annum
Month 60 Organic Block Certified 15ha organic certified