Granvora Feeds — Implementation Plan & Gantt Chart
The following implementation timeline outlines the critical path from investment close to full commercial operations. The total implementation period is estimated at 14 months from financial close to first commercial production.
Section 12 · Business Plan
Implementation Plan & Gantt Chart
The following implementation timeline outlines the critical path from investment close to full commercial operations. The total implementation period is estimated at 14 months from financial close to first commercial production.
The following implementation timeline outlines the critical path from investment close to full commercial operations. The total implementation period is estimated at 14 months from financial close to first commercial production.
12.1 Implementation Gantt Chart
Key implementation milestones and timelines:
| Activity / Workstream | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | M10 | M11 | M12 | M13 | M14 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Financial Close & Legal | ||||||||||||||
| Land Acquisition & Approvals | ||||||||||||||
| Environmental Impact Assessment | ||||||||||||||
| Site Preparation & Civil Works | ||||||||||||||
| Equipment Procurement | ||||||||||||||
| Building Construction | ||||||||||||||
| Equipment Installation | ||||||||||||||
| Utility Connections & Power | ||||||||||||||
| Staff Recruitment & Training | ||||||||||||||
| Commissioning & Testing | ||||||||||||||
| DALRRD Registration | ||||||||||||||
| Trial Production Runs | ||||||||||||||
| Commercial Production Launch |
12.2 Critical Milestones
| Milestone | Target Date | Dependencies |
|---|---|---|
| Financial Close | Month 1 | Investor commitment, legal documentation |
| Land Transfer Complete | Month 3 | Title deed, zoning confirmation |
| EIA Approval | Month 4 | DFFE approval process |
| Civil Works Complete | Month 7 | Weather, contractor performance |
| Equipment Delivered on Site | Month 6 | Import logistics, FX hedging |
| Building Handover | Month 10 | Occupancy certificate |
| Equipment Commissioning | Month 11 | OEM technicians, power availability |
| DALRRD Feed Registration | Month 12 | Product testing, documentation |
| Trial Production | Month 13 | Commissioning sign-off |
| First Commercial Sale | Month 14 | Customer contracts, logistics readiness |