Kasi Crisps — Implementation Roadmap
The implementation plan spans 14 months from financial close to commercial production commencement. The Gantt chart below illustrates the critical path, key dependencies, and parallel workstreams. The project management approach follows PMBOK guidelines with weekly steering committee reviews and monthly investor reporting.
Section 11 · Business Plan
Implementation Roadmap
The implementation plan spans 14 months from financial close to commercial production commencement. The Gantt chart below illustrates the critical path, key dependencies, and parallel workstreams. The project management approach follows PMBOK guidelines with weekly steering committee reviews and monthly investor reporting.
11.1 Critical Path & Milestones
The implementation plan spans 14 months from financial close to commercial production commencement. The Gantt chart below illustrates the critical path, key dependencies, and parallel workstreams. The project management approach follows PMBOK guidelines with weekly steering committee reviews and monthly investor reporting.
11.2 Key Milestones
| Milestone | Target Date | Dependencies | Status |
|---|---|---|---|
| Financial Close | Month 1 | Investor commitments, term sheet execution | In Progress |
| Company Registration & B-BBEE Setup | Month 2 | Legal counsel appointment | Pending |
| Site Lease Execution | Month 3 | SEZ allocation, lease negotiation | LOI Signed |
| Building Renovation Complete | Month 8 | Contractor appointment, permits | RFP Issued |
| Equipment Delivered & Installed | Month 8 | International procurement, shipping | Quotes Received |
| FSSC 22000 Certification | Month 11 | QMS documentation, audit | Gap Analysis Done |
| Trial Production Approved | Month 10 | Equipment commissioning, lab setup | Planned |
| First Commercial Shipment | Month 11 | Retailer listings, distribution setup | Negotiations Active |
| Phase 2 Expansion Decision | Month 36 | Year 2 financial performance | Planned |
11.3 Risk-Adjusted Timeline
The implementation schedule incorporates a 15% time contingency on critical-path activities (building renovation, equipment installation, and certification). In the event of delays, a pre-negotiated acceleration plan with contractors allows for double-shift work at a pre-agreed premium, reducing potential delays by up to 40%. The earliest possible commercial production date is Month 9 (best case), with Month 11 as the base case and Month 14 as the worst case.