KotaVille — Implementation Roadmap

The implementation plan spans 7.5 months from project initiation to grand opening of Unit 1, followed by a structured multi-unit expansion programme. The Gantt chart below illustrates the sequencing, dependencies, and duration of each workstream.

KotaVille (Kota Street Sandwich Company) Business PlanSection 10 › Implementation Roadmap

Section 10 · Business Plan

Implementation Roadmap

The implementation plan spans 7.5 months from project initiation to grand opening of Unit 1, followed by a structured multi-unit expansion programme. The Gantt chart below illustrates the sequencing, dependencies, and duration of each workstream.

10.1 Project Timeline

The implementation plan spans 7.5 months from project initiation to grand opening of Unit 1, followed by a structured multi-unit expansion programme. The Gantt chart below illustrates the sequencing, dependencies, and duration of each workstream.

Figure
Gantt Chart — visualised from the accompanying data.

10.2 Critical Milestones

Milestone Target Date Dependencies Success Criteria
Company Registration Month 1 None CIPC registration complete
Site Secured & Lease Signed Month 2.5 Market research Lease executed
Health Certificate Obtained Month 5 Fit-out complete CoA issued
Staff Fully Trained Month 6.5 Recruitment All certified
Soft Opening Month 7 All systems live Friends & family test
Grand Opening — Unit 1 Month 7.5 Soft opening review Full public operations
Unit 1 Break-even Month 17.5 Revenue ramp Monthly cash positive
Unit 2 Opening Month 14 Unit 1 proven Replication confirmed
Unit 3 & 4 Opening Month 24–30 Systems scaled Multi-unit profitable
Unit 5 + Franchise Pilot Month 36–42 Brand maturity Franchise manual ready

10.3 Multi-Unit Expansion Timeline

Unit Location Type Target Opening CapEx (ZAR) Monthly Revenue Target
Unit 1 (Flagship) Soweto high street Month 7.5 1,580,000 200,000
Unit 2 Taxi rank precinct Month 14 980,000 220,000
Unit 3 University campus Month 24 850,000 180,000
Unit 4 Shopping centre food court Month 30 720,000 250,000
Unit 5 CBD / office district Month 42 780,000 280,000

Note: Unit 2–5 CapEx decreases due to standardised design, supplier relationships, equipment reuse, and learnings from Unit 1. Each subsequent unit is expected to achieve break-even 2–3 months faster than its predecessor.