PetroStation SA — Implementation Roadmap

The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment…

PetroStation SA (Pty) Ltd Business PlanSection 12 › Implementation Roadmap

Section 12 · Business Plan

Implementation Roadmap

The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment…

12.1 Project Timeline

The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment fit-out — months 6-16), and operational launch (commissioning, staff training, regulatory inspection, and opening — months 16-18).

Figure
Gantt — visualised from the accompanying data.

Figure 12.1: 18-Month Implementation Gantt Chart

12.2 Key Milestones

Milestone Target Dependencies Success Criteria
Site Identified and Secured Month 3 Feasibility study, traffic counts Site meets oil company criteria
Petroleum Licence Granted Month 5 DMRE application, public participation Licence issued by DMRE
EIA Record of Decision Month 6 Environmental assessment Positive ROD from authorities
Funding Fully Secured Month 5 Business plan, licence, equity proof Loan approved and disbursed
Franchise Agreement Signed Month 7 Licence, funding, site confirmed Signed dealer/franchise agreement
Construction Commences Month 7 All approvals, contractor appointed Site handover to contractor
Tank Installation Complete Month 13 Civil works, tank delivery Tanks installed and pressure tested
Equipment Commissioning Month 15 Pumps, POS, canopy installed All systems operational
Regulatory Inspections Pass Month 16 Completed facility All clearances obtained
Grand Opening Month 17.5 Soft launch successful Opening event, trading commences
Break-even Throughput Achieved Month 32-34 Ramp-up strategy execution 300,000+ litres/month
Second Site Feasibility Month 36 Y1 performance confirmed Expansion plan approved

Table 12.1: Implementation Milestones