PetroStation SA — Implementation Roadmap
The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment…
Section 12 · Business Plan
Implementation Roadmap
The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment…
12.1 Project Timeline
The implementation plan spans 18 months from project initiation to operational stabilisation. The fuel station development lifecycle is characterised by three distinct phases: pre-development (licensing, environmental approvals, and site acquisition — months 1-6), construction and commissioning (civil works, tank installation, and equipment fit-out — months 6-16), and operational launch (commissioning, staff training, regulatory inspection, and opening — months 16-18).
Figure 12.1: 18-Month Implementation Gantt Chart
12.2 Key Milestones
| Milestone | Target | Dependencies | Success Criteria |
|---|---|---|---|
| Site Identified and Secured | Month 3 | Feasibility study, traffic counts | Site meets oil company criteria |
| Petroleum Licence Granted | Month 5 | DMRE application, public participation | Licence issued by DMRE |
| EIA Record of Decision | Month 6 | Environmental assessment | Positive ROD from authorities |
| Funding Fully Secured | Month 5 | Business plan, licence, equity proof | Loan approved and disbursed |
| Franchise Agreement Signed | Month 7 | Licence, funding, site confirmed | Signed dealer/franchise agreement |
| Construction Commences | Month 7 | All approvals, contractor appointed | Site handover to contractor |
| Tank Installation Complete | Month 13 | Civil works, tank delivery | Tanks installed and pressure tested |
| Equipment Commissioning | Month 15 | Pumps, POS, canopy installed | All systems operational |
| Regulatory Inspections Pass | Month 16 | Completed facility | All clearances obtained |
| Grand Opening | Month 17.5 | Soft launch successful | Opening event, trading commences |
| Break-even Throughput Achieved | Month 32-34 | Ramp-up strategy execution | 300,000+ litres/month |
| Second Site Feasibility | Month 36 | Y1 performance confirmed | Expansion plan approved |
Table 12.1: Implementation Milestones