Khanya Eggs Business Plan — Appendix B: Stage Capital Schedules

Detailed capital expenditure schedules for each of the five funding stages, by category and by year.

Appendix B: Stage Capital Schedules

Jump to section
On this page

  • B.1 Stage 1 — Year 1, 500 birds
  • B.2 Stage 2 — Year 2, 2 000 birds
  • B.3 Stage 3 — Year 3, 6 000 birds
  • B.4 Stage 4 — Year 4, 15 000 birds
  • B.5 Stage 5 — Year 5, 30 000 birds
  • B.6 Capital summary

B.1 Stage 1 — Year 1, 500 birds

Item

R’000

Share of stage

Site preparation, water connection and fencing

96

14.8%

Layer house, 500 birds

128

19.7%

Cages, feeders, drinkers and nest equipment

104

16.0%

Egg store, grading table and cold-safe area

62

9.5%

Water tanks, pump and reticulation

58

8.9%

Registration, permits and initial training

34

5.2%

Opening flock and feed working capital

168

25.8%

Total Stage 1

650

100.0%

B.2 Stage 2 — Year 2, 2 000 birds

Item

R’000

Share of stage

Layer house two, 1 500 birds

268

31.4%

Cages and equipment

196

23.0%

Feed store and bulk bin

82

9.6%

Second-hand delivery vehicle

165

19.3%

Working capital

142

16.6%

Total Stage 2

853

100.0%

B.3 Stage 3 — Year 3, 6 000 birds

Item

R’000

Share of stage

Layer house three, 4 000 birds

620

35.2%

Cages and equipment

452

25.7%

Egg grading and packing room

186

10.6%

Borehole and storage upgrade

148

8.4%

Biosecurity: perimeter, shower point, vehicle dip

138

7.8%

Working capital

216

12.3%

Total Stage 3

1 760

100.0%

B.4 Stage 4 — Year 4, 15 000 birds

Item

R’000

Share of stage

Layer houses four and five, 9 000 birds

1 420

34.6%

Cages, automatic drinkers and feed lines

1 080

26.3%

Solar PV, inverter and battery

650

15.9%

Cold room and egg handling upgrade

245

6.0%

Refrigerated delivery vehicle

385

9.4%

Working capital

320

7.8%

Total Stage 4

4 100

100.0%

B.5 Stage 5 — Year 5, 30 000 birds

Item

R’000

Share of stage

Layer houses six to eight, 15 000 birds

2 280

37.0%

Cages, feed and egg collection automation

1 760

28.5%

Automated grading and packing line

900

14.6%

On-farm feed mill and mixing plant

620

10.0%

Standby generator and electrical upgrade

185

3.0%

Working capital

425

6.9%

Total Stage 5

6 170

100.0%

B.6 Capital summary

Stage

Fixed assets

Working capital

Total

Cumulative

Stage 1

482

168

650

650

Stage 2

711

142

853

1 503

Stage 3

1 544

216

1 760

3 263

Stage 4

3 780

320

4 100

7 363

Stage 5

5 745

425

6 170

13 533

Total

12 262

1 271

13 533