TerraNova Copper & Minerals Group Business Plan — Implementation Roadmap

Jump to sectionAll 21 pages
Section 10 · 11 of 21

Implementation Roadmap

The plan is delivered in three phases over ten years, with the first five years, the funded period, taking the mine from financial close to nameplate production. The Gantt chart below sets out the critical path, milestones and dependencies. The defining feature of a block-cave development is that substantial capital must be committed before meaningful production begins; the schedule and its dependencies are therefore the backbone of the risk-management framework.

Figure 14. Mine-development roadmap, milestones and dependencies

Phase detail

  • Phase 1 (Years 1–3) — mine development, box-cut and decline, concentrator construction, vermiculite and magnetite plants, and first ore. Capital is at its heaviest and production is ramping.
  • Phase 2 (Years 3–5) — smelter and refinery commissioning, copper-rod plant, chemicals plant, renewable energy, export-terminal partnerships, and ramp to nameplate.
  • Phase 3 (Years 5–10) — battery-minerals expansion, regional copper acquisitions, downstream beneficiation plants, and listing or strategic-exit readiness.

Critical milestones and dependencies

The following milestones sit on the critical path; each is a condition for the next, and several are drawdown gates subject to independent-engineer verification.

Milestone

Timing

Dependency / gate

Financial close & first drawdown

Year 1 Q1

Equity committed; conditions precedent met

Permitting & mining right confirmed

Year 1 H1

Environmental authorisation; SLP approved

Box-cut & decline established

Year 1–2

Financial close

First ore & concentrator commissioning

Year 2

Decline & concentrator complete

Smelter commissioning

Year 3

Concentrate availability

Refinery & rod plant online

Year 3–4

Smelter anode supply

Ramp to nameplate

Year 5

Cave maturity; all plant commissioned

Exit readiness (listing/strategic)

Year 5+

Steady-state production; governance in place

Analyst flagThe schedule is the risk

Because block-cave establishment precedes meaningful cash flow, any slippage in decline development, cave establishment or smelter commissioning directly delays revenue while interest continues to accrue, the mechanism behind the early-year losses. The plan mitigates this with experienced block-cave contractors, staged commissioning, a debt-service reserve account and construction contingency, but schedule discipline is the single most important execution priority.