Urbanova — Implementation Roadmap

The phased implementation roadmap and the milestones underpinning Urbanova.

Urbanova Business PlanSection 19 › Implementation Roadmap

Section 19 · Business Plan

Implementation Roadmap

The phased implementation roadmap and the milestones underpinning Urbanova.

The programme spans financial close in mid-2027 through
exit-readiness in FY2031. Critical-path dependencies: capital raise
precedes Phase 1 land assembly at scale; rezoning and bulk-services
approvals gate construction start; Phase 1 stabilisation evidence
(occupancy ≥90%, collections ≥97%) gates Phase 2 debt drawdowns; and
refinancing/capital-markets readiness gates exit.

Figure 9
Figure 9: Implementation Gantt — milestones, timelines and dependencies, 2026–2031
Milestone Target date Dependency
Financial close (equity + senior facilities) Jun 2027 Anchor DFI commitment; named executive team
Phase 1 land assembly complete Sep 2027 Financial close
First 1,200 units income-producing Dec 2027 Construction start Apr 2027
Phase 1 stabilisation (≥90% occupancy) Jun 2029 Lease-up engine; tenant app live
Phase 2 construction start (CPT/DBN) Jul 2028 Phase 2 approvals; Tranche 2 debt
12,500 cumulative units Dec 2030 Phase 2 delivery
Amortisation commences — DSCR watch period Jan 2029 Grace period expiry (Finding 2)
20,000 units; portfolio R18.8bn (sponsor FV) Dec 2031 Phase 3 delivery
Exit preparation (REIT listing / trade sale) FY2031 Audited stabilised NOI; refinancing

Confidential — this business plan is provided to prospective investors and lenders for evaluation purposes only and may not be reproduced or distributed without the written consent of Urbanova Living Developments (Pty) Ltd.