Tarlton Beetroot Business Plan — Capital Expenditure and Working Capital

R27.87m of capital concentrated in Year 3, and the working capital cycle through planting and harvest.

Section 26 of 37

Capital Expenditure and Working Capital

Jump to section

R31.6 million of capital expenditure, of which R10.6 million is land and R0.97 million is written off when Phase 1 is vacated.

Tranche A capital expenditure

Table 39 Phase 1 capital expenditure schedule

Item

R

Month

Transfers to Phase 2

Drip irrigation, 1 ha, with 3 ha mainline and filtration

265 000

1

Yes

Borehole equipping, pump, storage and reticulation

310 000

1

No

Land preparation, ripping and soil correction

78 000

1

No

Tractor, 55 kW (used) and implement set

685 000

1

Yes

Precision vacuum seeder, two-row

165 000

1

Yes

Light delivery vehicle, one tonne (used)

340 000

1

Yes

Perimeter fencing, field store and ablutions

210 000

2

No

Scales, harvest crates and field equipment

88 000

2

Yes

IT, farm-management software and connectivity

62 000

1

Yes

Pre-operating: incorporation, water registration, trials

185 000

1

No

Contingency at 8 per cent

186 000

3

No

Total Tranche A capital expenditure

2 574 000

Transferable versus sunk Phase 1 capital
Figure 1. Transferable versus sunk Phase 1 capital.

Tranche B capital expenditure

Table 40 Phase 2 capital expenditure schedule

Item

R

Month

Class

Farm acquisition, 85 ha (62 ha arable, 55 ha water-entitled)

9 900 000

28

land

Transfer duty, conveyancing and technical due diligence

720 000

27

land

Bulk irrigation: dam, pump station, mainline, filtration

2 900 000

29

farm

In-field irrigation, first 34 ha

1 970 000

30

farm

Land preparation, ripping and liming, 34 ha

1 190 000

30

farm

Packhouse structure with root wash, grade and pack line

2 900 000

31

plant

Cold rooms (two) and forklift

900 000

33

plant

Solar PV, 100 kWp

1 150 000

32

plant

Tractors (two, 75 kW), implements and trailers

1 720 000

30

plant

Refrigerated truck and light delivery vehicle

1 320 000

33

vehicle

Staff housing, internal roads, workshop and security

940 000

32

farm

Certification, ERP and traceability systems

380 000

34

plant

In-field irrigation and land preparation, further 20 ha

1 380 000

42

farm

Contingency at 7 per cent

1 880 000

34

farm

Total Tranche B capital expenditure

29 250 000

Working capital

Table 41 Working capital and cash conversion, R thousand

R’000

Year 1
FY2028

Year 2
FY2029

Year 3
FY2030

Year 4
FY2031

Year 5
FY2032

Trade receivables

22

106

782

1 621

2 463

Growing crop

34

145

674

692

922

VAT receivable

22

47

143

228

308

Trade payables

(177)

(374)

(1 144)

(1 826)

(2 470)

Net working capital

(99)

(76)

456

715

1 223

Debtor days

22

24

60

32

35

Creditor days

214

118

152

69

66

Cash conversion cycle, days

(150)

(49)

(3)

(10)

(7)

26