Mainstreet Junction Business Plan — Implementation Timeline

The timeline from funding close to first fuel sale, covering licensing, construction, tank installation and commissioning.

Implementation Timeline

Jump to section
Implementation roadmap — approvals, licensing and construction
Figure 24. Implementation roadmap — approvals, licensing and construction.

Phase

Months

Key activities

Capital committed

1. Site securing and feasibility

0–3

Option or conditional purchase agreement; independent seven-day traffic count split light and heavy; economic viability study; preliminary oil company engagement

Option fee and study costs only

2. Statutory approvals

3–12

Rezoning application; environmental authorisation under NEMA; road access approval; heritage and geotechnical investigation where triggered

Professional fees of approximately R1.8m

3. Licensing and financial close

9–15

Site and retail licence applications with the DMPR; ten-year supply and branding agreement; quick-service restaurant lease signed as a condition precedent

Land acquisition of R8.5m; bulk of equity drawn

4. Construction and commissioning

15–24

Earthworks and civils; tank installation and pipework; canopy, dispensers and forecourt controller; shop building and fit-out; car wash; 60 kWp solar

Balance of R44.5m project cost

5. Trading and ramp

24–36

Opening at 340 000 litres a month ramping to 400 000; twelve-month capital moratorium runs; convenience format establishing

Working capital buffer of R1.4m

16.1 Critical dependencies and gates

Gate

When

Condition

Consequence if not met

Gate 1: traffic count supports the case

Month 3

A seven-day count demonstrating a defensible path to at least 400 000 litres a month

Do not exercise the option. The option fee is the entire loss, and it is the cheapest possible outcome

Gate 2: statutory approvals secured

Month 12

Rezoning granted and environmental authorisation issued

Do not acquire the land. Zoning and NEMA are the critical path and neither can be bought

Gate 3: financial close

Month 15

Site and retail licences issued; ten-year supply agreement signed; quick-service lease signed

Do not commence construction. The QSR lease is a condition precedent because it underwrites the shop conversion assumption

Gate 4: commissioning

Month 23

Calibration, municipal sign-off, staff trained, wet stock systems operating

Do not open. A forecourt that opens without wet stock discipline never establishes it

Gate 5: cover clears the covenant

Month 36

Debt service cover above 1.50 times

No distribution. The distribution gate is set above the covenant deliberately