Sakhile Construction Business Plan — Strategy: Private Work First

Why the plan targets private clients before public tenders, what that does to payment terms and cash, and when government work becomes viable.

Strategy: Private Work First

Jump to section

The instinctive path for an emerging contractor is straight into public tenders. This plan deliberately does the opposite in the early years, for two reasons that are worth stating plainly.

  • CIDB grading caps public-sector contract value only. Private work is not grade-limited. A Grade 1 contractor may lawfully build a R4 million private warehouse. That is how a new company builds the turnover and the completed-contract track record that unlock Grade 3, 4 and 5 for public work.
  • Private clients pay in about 38 days; public clients take 68. Every rand of private turnover consumes roughly half the working capital of the same rand of public turnover. In the years when capital is scarcest, that difference is decisive.
Revenue mix. The business starts 75% private and shifts toward public work only as capital, grade and payment-cycle tolerance allow
Figure 5. Revenue mix. The business starts 75% private and shifts toward public work only as capital, grade and payment-cycle tolerance allow.
Contracts run and average contract value
Figure 6. Contracts run and average contract value.

Year 1

Year 2

Year 3

Year 4

Year 5

Private turnover, R’000

3 150

5 600

9 500

16 000

24 000

Public turnover, R’000

1 050

3 900

9 500

18 000

28 000

Total turnover, R’000

4 200

9 500

19 000

34 000

52 000

Public share

25.0%

41.1%

50.0%

52.9%

53.8%

Blended debtor days

45.5

50.3

53.0

53.9

54.2

Contracts run

6

9

12

15

18

Average contract, R’000

700 000

1 055 556

1 583 333

2 266 667

2 888 889

The blended debtor days rise from 45.5 to 54.2 as the public share moves from 25 per cent to 53.8 per cent. That deterioration is deliberate and funded: it is the price of building the public track record that the grade ladder requires, and it is why the growth equity arrives at Year 3 rather than at inception.

4.1 Why private work is the right starting point

  • No grade limit. A Grade 1 contractor may lawfully build a R4 million private warehouse; the same contractor is capped at R500 000 on a public award.
  • Thirty days sooner. Private clients pay at about 38 days against 68 modelled for public work, so every rand of private turnover consumes roughly half the working capital.
  • Advance and milestone payments are frequently negotiable on private contracts and very rarely available on public ones. That is the cheapest working capital a contractor can obtain.
  • Track record credit is identical, provided the project is registered. A completed private contract counts toward works capability exactly as a public one does.
  • Guarantees are required on larger private contracts only, against most public awards — which preserves scarce guarantee facility capacity in the years when it is smallest.
  • Awards are relationship-driven rather than tendered, which suits a company with no public track record and no scored history to point at.

The commercial logic follows. In Years 1 and 2 the company has no capital to spare and no track record to trade on, and private work supplies both. By Year 3 the growth equity has arrived and the facility is established, which is when public work becomes affordable rather than merely attractive.