Sakhile Construction Business Plan — Sensitivity and Scenarios

How the plan responds to margin erosion, payment delay and contract volume moving against it, with downside and upside cases.

Sensitivity and Scenarios

Jump to section
On this page

  • 16.1 Single-variable sensitivity
  • 16.2 Scenarios

16.1 Single-variable sensitivity

Sensitivity of Year 5 EBITDA
Figure 20. Sensitivity of Year 5 EBITDA.

Driver

Effect on Year 5 EBITDA

As a share of base

Gross margin ±3 percentage points

±R1.56m

±44%

Turnover ±15%

±R1.46m

±41%

Materials cost ±10%

±R1.95m

±55%

Site labour ±10%

±R1.14m

±32%

Overhead ±10%

±R0.62m

±18%

Debtor days +30 (financing cost)

(R0.62m)

±18%

Year 5 base case EBITDA

R3.52m

Materials at R1.95 million for a ten per cent movement is the largest single exposure, followed by gross margin at R1.56 million for three percentage points and turnover at R1.46 million for fifteen per cent. All three are estimating exposures rather than market ones: a ten per cent materials movement is priced into a bid or it is not, and a three-point margin miss is an estimating failure by definition.

Year 5 EBITDA across gross margin and debtor days
Figure 21. Year 5 EBITDA across gross margin and debtor days.

The grid makes the central point of this plan visible. Reading across a row, debtor days change nothing at the EBITDA line — they change the financing cost below it and the facility required to trade at all. Reading down a column, three percentage points of gross margin moves EBITDA by R1.56 million, which is 44 per cent of the base case. Payment delay is a funding problem; margin is a survival problem, and they are managed by different people using different disciplines.

16.2 Scenarios

Year 5 EBITDA and profit after tax across scenarios
Figure 22. Year 5 EBITDA and profit after tax across scenarios.

Scenario

Definition

Year 5 turnover

Year 5 EBITDA

Profit after tax

Base

The plan as presented: R52.00m turnover at 18.7% gross margin, 54 debtor days.

R52.00m

R3.52m

R0.31m

Payment delay

Debtor days 30 above plan; the facility must carry it and the financing cost lands in the P&L.

R52.00m

R2.90m

(R0.31m)

Order book shortfall

Turnover 15% below plan on a delayed public award or a cancelled private project.

R44.20m

R2.06m

(R1.15m)

Margin miss

Gross margin three points below plan — the difference between good and poor estimating.

R52.00m

R1.96m

(R1.25m)

Margin and delay

Three points of margin lost and 30 additional debtor days in the same year.

R52.00m

R1.34m

(R1.87m)

Previous section15. Break-Even