Sakhile Construction Business Plan — Appendix D: Risk Register

Detailed risk register scoring likelihood and impact across contract, financial, operational and compliance risks with mitigations.

Appendix D: Risk Register

Jump to section

Risk

Likelihood

Impact

Mitigation

Owner

Estimating error

High

Very High

Priced bill of quantities on every bid; labour constants from the company’s own completed contracts; refreshed material quotations; monthly cost report per contract. Three points of margin is R1.56m against R3.52m of EBITDA.

Contracts director

Payment delay beyond plan

High

Very High

Complete claim documentation; monthly certification; disciplined chasing from day one; delay priced into preliminaries; public order book capped against facility capacity. 60% of public payments are delayed beyond 30 days.

Finance

Working capital exhaustion

High

Very High

Growth equity at Year 3; facility sized to the debtor book; the rule that the public order book must be fundable through a 90-day delay. Net working capital reaches R9.62m.

Board

Register of Projects failure

Medium

High

Written confirmation of registration at every award, chased within the 21 days. An unregistered project earns no works capability credit whatever its value.

Contracts director

Registration lapse

Low

Very High

Diarised renewal calendar with a named owner. Auto-suspension from 1 January 2026 removes the company from the Register the day after expiry, with no grace period.

Finance

Materials price movement

High

High

Quotations refreshed at bid; fixed-price subcontracts where obtainable; escalation clauses on longer contracts. A 10% movement is R1.95m.

Estimating

Retention not claimed

Medium

High

Retention register recording every contract, practical completion date, defects liability expiry and amount due. R4.21m is released in Year 5 alone.

Finance

Order book shortfall

Medium

High

Margin of safety is 16.0% on the finance-inclusive break-even — roughly two contracts. Private and public work run in parallel to reduce correlation.

Contracts director

Guarantee capacity exhausted

Medium

Medium

Capacity is sized against the balance sheet; retained earnings expand it. A fully committed facility caps the order book regardless of demand.

Board

Skilled site staff loss

Medium

High

The sector describes skills as very problematic. Site management appointed at Year 3 and retained; training funded from Year 4.

Contracts director

Contractual risk transfer

High

Medium

Contract terms read and priced at bid rather than accepted. A risk transferred is a cost, and it belongs in the rate.

Estimating

Client insolvency or project cancellation

Low

High

Credit assessment on private clients; concentration limits; work in progress kept current through monthly certification.

Finance