Sakhile Construction Business Plan — The Working Capital Problem
Why construction consumes cash as it grows: an 18.5% of turnover working capital requirement and a 66-day cash cycle that must be funded.
The Working Capital Problem
Jump to section
- Overview & contents
- i. Important Notice
- 1. Executive Summary
- 2. The CIDB Grading Ladder
- 3. The Market in 2026
- 4. Strategy: Private Work First
- 5. SWOT and Competitive Position
- 6. The Working Capital Problem
- 7. Retention and Guarantees
- 8. Unit Economics of a Contract
- 9. The Five-Year Roadmap and Gates
- 10. Funding
- 11. Estimating and Contract Control
- 12. People and Plant
- 13. Compliance and Registrations
- 14. Financial Projections
- 15. Break-Even
- 16. Sensitivity and Scenarios
- 17. Risk Management
- 18. Implementation Timeline
- 19. Returns
- 20. Key Performance Indicators
- 21. Key Assumptions
- 22. Conclusion
- A. Appendix A: Consolidated Financial Summary
- B. Appendix B: Capital Schedules
- C. Appendix C: Funding and Debt Schedules
- D. Appendix D: Risk Register
- E. Appendix E: Glossary
|
Component |
Year 5 |
What it is |
|---|---|---|
|
Trade debtors |
R7.72m |
Certified work invoiced and unpaid. Public at 68 days, private at 38. |
|
Retention receivable |
R2.86m |
10.0% withheld from every certificate, released half at practical completion and half after the defects liability period. |
|
Work in progress |
R2.20m |
Work done on site but not yet certified. Roughly 19.0 days of direct cost. |
|
Less trade creditors |
(R3.16m) |
Materials and subcontractors at 42 days. Merchants now work on 30-day terms at best and increasingly cash on delivery. |
|
Net working capital |
R9.62m |
18.5% of turnover |
|
R’000 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|---|---|---|---|---|---|
|
Trade debtors |
524 |
1 309 |
2 759 |
5 021 |
7 722 |
|
Retention receivable |
231 |
523 |
1 045 |
1 870 |
2 860 |
|
Work in progress |
233 |
478 |
903 |
1 526 |
2 201 |
|
Less trade creditors |
(265) |
(593) |
(1 174) |
(2 083) |
(3 162) |
|
Net working capital |
723 |
1 717 |
3 533 |
6 334 |
9 621 |
|
As a share of turnover |
17.2% |
18.1% |
18.6% |
18.6% |
18.5% |
|
Absorbed in the year |
(723) |
(994) |
(1 816) |
(2 801) |
(3 287) |
The cycle is 62 days in Year 1 and 66 by Year 5, peaking at 67 in Years 3 and 4 when the public share rises fastest. Debtor days contribute 54.2, retention a further 20.1 and work in progress 19.0, against only 27.3 days of creditor funding. Every one of those components is a decision the contractor makes or a term the client imposes; none of them is inevitable in the amounts shown.
6.1 The six disciplines that shorten the cycle
- Never submit a claim without complete supporting evidence. The clock only starts on a valid invoice, and a missing order number or a claim that does not match the order is the most common cause of delay. This is a documentation problem before it is a finance problem.
- Certify early and often. Monthly certificates, submitted on the day they fall due, with measurements agreed with the client’s agent in advance rather than argued afterwards.
- Chase from day one, not day sixty. Contractors who survive public work are not the ones who complain about late payment; they are the ones who chase it with discipline and a named person responsible.
- Negotiate advance and milestone payments on private contracts wherever possible, rather than payment on completion. Private clients are far more willing to agree this than public bodies, and it is the cheapest working capital available.
- Price the delay into the bid. Bidding public work at the same rate as a fast-paying private client means funding the state’s delay out of your own margin. The financing cost of 75 days should sit in the preliminaries.
- Cap concentration. No more public work at once than the facility can fund through the longest realistic delay.