Sakhile Construction Business Plan — Retention and Guarantees
How retention held back on every contract and the guarantees clients demand tie up capital, and what that costs the contractor.
Retention and Guarantees
Jump to section
- Overview & contents
- i. Important Notice
- 1. Executive Summary
- 2. The CIDB Grading Ladder
- 3. The Market in 2026
- 4. Strategy: Private Work First
- 5. SWOT and Competitive Position
- 6. The Working Capital Problem
- 7. Retention and Guarantees
- 8. Unit Economics of a Contract
- 9. The Five-Year Roadmap and Gates
- 10. Funding
- 11. Estimating and Contract Control
- 12. People and Plant
- 13. Compliance and Registrations
- 14. Financial Projections
- 15. Break-Even
- 16. Sensitivity and Scenarios
- 17. Risk Management
- 18. Implementation Timeline
- 19. Returns
- 20. Key Performance Indicators
- 21. Key Assumptions
- 22. Conclusion
- A. Appendix A: Consolidated Financial Summary
- B. Appendix B: Capital Schedules
- C. Appendix C: Funding and Debt Schedules
- D. Appendix D: Risk Register
- E. Appendix E: Glossary
- 7.1 Retention
- 7.2 Guarantees
Two contractual mechanisms take cash out of a contractor’s hands without appearing as a cost. Both are standard, both are non-negotiable in practice, and both must be planned for rather than discovered.
7.1 Retention
|
R’000 |
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|---|---|---|---|---|---|
|
Turnover |
4 200 |
9 500 |
19 000 |
34 000 |
52 000 |
|
Retention withheld in the year at 10.0% |
420 |
950 |
1 900 |
3 400 |
5 200 |
|
Retention released in the year |
189 |
658 |
1 378 |
2 575 |
4 210 |
|
Retention outstanding at year end |
231 |
523 |
1 045 |
1 870 |
2 860 |
|
As a share of turnover |
5.5% |
5.5% |
5.5% |
5.5% |
5.5% |
|
Days of turnover |
20.1 |
20.1 |
20.1 |
20.1 |
20.1 |
Two different figures are commonly confused. R5.20 million is withheld during Year 5, being ten per cent of every certificate issued. R2.86 million is the balance still outstanding at the year end, after R4.21 million of releases from earlier contracts. The first is what the business gives up during the year; the second is what it is owed at a point in time. A contractor who plans against the wrong one will either over-fund or, more commonly, be surprised.
7.2 Guarantees
|
Instrument |
Typical value |
When required |
Effect |
|---|---|---|---|
|
Performance guarantee |
5% to 10% of contract value |
At award on most public and larger private contracts |
Contingent, not cash, but consumes guarantee facility capacity |
|
Advance payment guarantee |
Equal to the advance |
Where an advance payment is negotiated |
Converts a cash benefit into a facility commitment |
|
Retention guarantee |
Equal to retention withheld |
Optionally, in lieu of cash retention |
Releases the cash but at a fee and against facility capacity |
|
Defects liability guarantee |
2.5% to 5% of contract value |
At practical completion in some contracts |
Extends the commitment through the defects period |
|
Year 1 |
Year 2 |
Year 3 |
Year 4 |
Year 5 |
|
|---|---|---|---|---|---|
|
Guarantee facility fees, R’000 |
— |
45 |
130 |
260 |
420 |
|
As a share of turnover |
— |
0.47% |
0.68% |
0.76% |
0.81% |
Guarantee fees reach R420 000 by Year 5, 0.81 per cent of turnover. The fee itself is modest; the constraint is capacity. A guarantee facility is sized by the provider against the balance sheet, and a contractor whose facility is fully committed against existing contracts cannot bid new work regardless of how attractive it is. Guarantee capacity, not cash, is frequently what caps a growing contractor’s order book — and it is another reason retained earnings matter more here than in most businesses.