Sakhile Construction Business Plan — Retention and Guarantees

How retention held back on every contract and the guarantees clients demand tie up capital, and what that costs the contractor.

Retention and Guarantees

Jump to section
On this page

  • 7.1 Retention
  • 7.2 Guarantees

Two contractual mechanisms take cash out of a contractor’s hands without appearing as a cost. Both are standard, both are non-negotiable in practice, and both must be planned for rather than discovered.

7.1 Retention

Retention withheld against retention still outstanding
Figure 10. Retention withheld against retention still outstanding.

R’000

Year 1

Year 2

Year 3

Year 4

Year 5

Turnover

4 200

9 500

19 000

34 000

52 000

Retention withheld in the year at 10.0%

420

950

1 900

3 400

5 200

Retention released in the year

189

658

1 378

2 575

4 210

Retention outstanding at year end

231

523

1 045

1 870

2 860

As a share of turnover

5.5%

5.5%

5.5%

5.5%

5.5%

Days of turnover

20.1

20.1

20.1

20.1

20.1

Two different figures are commonly confused. R5.20 million is withheld during Year 5, being ten per cent of every certificate issued. R2.86 million is the balance still outstanding at the year end, after R4.21 million of releases from earlier contracts. The first is what the business gives up during the year; the second is what it is owed at a point in time. A contractor who plans against the wrong one will either over-fund or, more commonly, be surprised.

7.2 Guarantees

Instrument

Typical value

When required

Effect

Performance guarantee

5% to 10% of contract value

At award on most public and larger private contracts

Contingent, not cash, but consumes guarantee facility capacity

Advance payment guarantee

Equal to the advance

Where an advance payment is negotiated

Converts a cash benefit into a facility commitment

Retention guarantee

Equal to retention withheld

Optionally, in lieu of cash retention

Releases the cash but at a fee and against facility capacity

Defects liability guarantee

2.5% to 5% of contract value

At practical completion in some contracts

Extends the commitment through the defects period

Year 1

Year 2

Year 3

Year 4

Year 5

Guarantee facility fees, R’000

45

130

260

420

As a share of turnover

0.47%

0.68%

0.76%

0.81%

Guarantee fees reach R420 000 by Year 5, 0.81 per cent of turnover. The fee itself is modest; the constraint is capacity. A guarantee facility is sized by the provider against the balance sheet, and a contractor whose facility is fully committed against existing contracts cannot bid new work regardless of how attractive it is. Guarantee capacity, not cash, is frequently what caps a growing contractor’s order book — and it is another reason retained earnings matter more here than in most businesses.