Two Seasons Garlic Business Plan — Implementation Roadmap

The phases from 12 hectares to 92 across two provinces, dependencies and the gate at each stage.

Implementation Roadmap

Jump to section

Sixty months in five phases; the critical path runs through seed multiplication and the packhouse audit, and each funding round is timed to a planting window.

Implementation Gantt chart, months from seed close (July 2026)
Figure 10. Implementation Gantt chart, months from seed close (July 2026).

Phase

Months

Workstream

Key milestones and deliverables

Dependencies

Responsible

Pre-launch

0–10

Legal, land, water, planting stock, infrastructure

Seed close; leases and water executed; CPs satisfied; cultivar trial results; irrigation on both blocks; curing sheds; core mechanisation

Seed round; term facility credit approval

CEO, FD, Ops

Launch

7–19

First plantings; first harvest

12 ha planted (Feb–Jun 2027); first Limpopo harvest Sep–Oct 2027; Karoo Dec–Jan; 45 t seed selected and stored

Irrigation complete; planting stock delivered

Ops

Ramp-up

13–30

Series A; packhouse; retail trial; 28 → 48 ha

Series A close M14; packhouse built M14–22; GFSI audit M22–26; retail trial FY2028; programme listing FY2029

Seed retained at FY2028 harvest; Series A

FD, Commercial

Scale-up

31–48

Series B; peeling line; food service; export; 70 ha

Series B close M33; peeling line commissioned M40; peeled programme M44; SADC agencies; solar roll-out

Series B; listing secured

FD, Commercial, Ops

Expansion

49–60

92 ha; seed sales trial; FY2032 decision

92 ha planted; 176 t seed retained; certified planting-stock trial; expansion decision by board

Market absorption evidence

Board

Table 34. Implementation phases, milestones and dependencies.

The critical path is agronomic, not financial. Series A must close before the FY2029 planting window because the seed retained at the FY2028 harvest determines whether that area can be planted at all; capital arriving after that window is a season late regardless of how much of it there is. The packhouse audit must be passed before the FY2029 listing is sought, which places the build in months 14–22 and the audit in months 22–26. Each round is opened three months before its required close to allow for slippage.