Khanya Cold Chain Business Plan — Risk Analysis

The principal risks facing a start-up cold store, from occupancy shortfall and tariff escalation to refrigeration failure, with controls.

Risk Analysis

Jump to section
On this page

  • 12.1 The risks that matter
  • 12.2 Sensitivity
  • 12.3 Scenarios and the downside
  • 12.4 Trigger points

12.1 The risks that matter

Occupancy failing to ramp is the dominant risk and it is not close. Break-even including debt service is 56 per cent against a Year 1 plan of 46 per cent, and an eight-point shortfall removes R8 498 791 of Year 3 EBITDA, nearly half of it. It is managed by anchor contracting of 1 200 positions before drawdown, by the pre-committed trigger points in Section 12.4, and by a commercial approach that treats an occupied pallet at a poor rate as better than an empty position drawing power.

Covenant breach in Years 1 and 2 is close to certain on a standard test. Cover of 0.22 times and 1.15 times is below a 1.30 times covenant, and it must be addressed in the term sheet through a Year 3 covenant start, an interest reserve or a longer moratorium, not discovered when the first test date arrives.

Capital cost overrun is the risk that is cheapest to eliminate. Refrigeration and envelope are 50 per cent of capital expenditure on indicative pricing, and a 15 per cent overrun on those two lines alone is R6 675 000. Firm fixed-price contracting with retention before drawdown removes most of it.

Lease renewal and landlord leverage is a structural exposure created by the decision to lease. R89 800 000 of plant fixed into a building the business does not own gives the landlord considerable negotiating power at renewal. A ten-year term with tenant renewal options is a condition of proceeding, and a purchase option would remove the risk entirely.

Ammonia is a regulatory and safety exposure rather than a line item. A plant of this size is a major hazard installation requiring risk assessment, an emergency plan tested with the local authority and competent-person inspections. The approval timeline is a gating item in the construction programme capable of delaying commissioning by months, and the residual safety risk is managed through the competent-person regime and insurance rather than eliminated.

12.2 Sensitivity

Year 3 EBITDA sensitivity
Figure 21. Year 3 EBITDA sensitivity.

Driver

Downside

Upside

Swing

As a share of base EBITDA

Occupancy ±8 points

14 807 526

23 306 316

8 498 791

45%

Storage tariff ±6%

15 302 334

22 811 508

7 509 175

39%

Occupancy ±4 points

16 932 224

21 181 618

4 249 395

22%

Other operating costs ±10%

17 650 393

20 463 449

2 813 056

15%

Electricity cost ±20%

18 475 934

19 637 908

1 161 973

6%

Electricity cost ±10%

18 766 428

19 347 414

580 986

3%

Base case Year 3 EBITDA

19 056 921

12.3 Scenarios and the downside

EBITDA by scenario
Figure 22. EBITDA by scenario.

Downside

Base

Upside

Occupancy assumption

−13 points

As modelled

+5.5 points

Tariff assumption

−6%

As modelled

+3.5%

Electricity assumption

+14%

As modelled

−4%

Year 1 EBITDA

(6 159 380)

1 418 599

5 135 068

Year 3 EBITDA

8 466 455

19 056 921

24 396 803

Year 5 EBITDA

13 993 106

26 819 815

33 333 192

Year 5 EBITDA margin

19.6%

31.9%

36.8%

Project IRR

−1.7%

18.2%

23.8%

Cash position, base against downside
Figure 23. Cash position, base against downside.

Downside case (R)

Year 1

Year 2

Year 3

Year 4

Year 5

Occupancy

33%

55%

66%

72%

75%

Revenue

20 590 281

38 053 425

52 182 729

63 202 294

71 396 760

EBITDA

(6 159 380)

2 898 206

8 466 455

12 127 192

13 993 106

Debt service cover

-0.98x

0.28x

0.80x

1.15x

1.33x

Cash / (funding shortfall)

(1 346 640)

(16 951 723)

(27 378 702)

(32 680 283)

(34 658 147)

Book value of equity

29 954 311

17 054 526

9 333 301

5 132 496

2 916 744

12.4 Trigger points

Point

Trigger

Committed response

Month 6

Below 32% occupancy

Freeze vehicle purchases and all discretionary capital. Reprice to fill space, accepting lower rates for term

Month 12

Below 40% average occupancy

Formal lender review. Offer short-term overflow contracts at marginal rates; an occupied pallet at a poor rate beats an empty position

Month 18

Blast tunnels below 35% utilisation

The premium service is not selling. Review pricing, sales coverage and whether the capacity was over-specified

Month 24

Debt service cover below 1.00x

Approach lenders for restructuring before breach. A negotiated extension is far cheaper than a default

Month 30

Cash below R6m with the revolver fully drawn

Initiate an equity raise. Do not fund operations from the revolver beyond this point

Month 36

Below 60% occupancy

The base case has failed. Evaluate a sale of the operating business to a national operator, who can fill the building with volume the company cannot win

These are adopted as board policy before drawdown rather than debated when the trigger arrives. The month-36 trigger deserves emphasis. A half-full cold store is worth considerably more to a national operator with national volume than it is to the founders, and the moment to explore that is while the business still has cash and a lender who is being kept informed, not after a default.