Khanya Cold Chain Business Plan — Implementation Roadmap

The timeline from financial close to commissioning on 1 March 2027, covering construction, plant installation and tenant onboarding.

Implementation Roadmap

Jump to section
On this page

  • 13.1 Development programme
  • 13.2 Critical dependencies
  • 13.3 Conditions precedent to drawdown
  • 13.4 Operating milestones after commissioning
  • 13.5 Where the eighteen months before commissioning go
Implementation roadmap — anchor tenancy and ammonia approval gate the programme
Figure 24. Implementation roadmap — anchor tenancy and ammonia approval gate the programme.

13.1 Development programme

Phase

Months

Activities

Gate

1. Pre-development

0–4

Incorporate; appoint executive team; agree heads of terms on the lease; firm fixed-price refrigeration and envelope tender

Anchor tenancy of 1 200 pallets contracted; notified maximum demand and Megaflex tariff confirmed in writing

2. Approvals and close

2–9

Ammonia major hazard installation risk assessment and emergency plan; municipal and environmental approvals; refrigerant handling registration; funding close

MHI approval issued — the gating item in the programme. Equity drawn and facilities closed

3. Construction

7–17

Lease signed; tenant installation of envelope and panelling; refrigeration plant, ammonia charge and commissioning; solar, battery and standby; racking, docks and materials handling; WMS and control room

Plant validated, temperature pull-down complete

4. Year 1 trading

17–29

Commissioning 1 March 2027; ramp from 19% to 55% occupancy; three rigids operating; FSSC 22000 or BRCGS certification

Certification achieved by month 12 of trading

5. Year 2 and 3

29–53

Occupancy to 68% then 79%; fleet to 6 then 9 vehicles; first capital repayment falls due at the end of the moratorium

Year 3 debt service cover clears 1.30x at 79% occupancy

13.2 Critical dependencies

Dependency

What it gates

Why it cannot be accelerated

Anchor tenancy of 1 200 positions

Every drawdown of capital

Year 1 occupancy of 46% against a 56% break-even is where this plan is most exposed. Contracts take six to nine months to close

Ammonia major hazard installation approval

Commissioning

A statutory process with mandatory risk assessment and emergency planning. Capable of delaying commissioning by months and not within the developer’s control

Notified maximum demand at the connection

The entire energy thesis

A refrigeration plant of this size cannot simply be connected wherever a building is cheapest. Written confirmation is a condition precedent

Firm refrigeration and envelope pricing

Construction drawdown

50% of capital expenditure on indicative pricing. A 15% overrun is R6 675 000

Ten-year lease with renewal options

Fixing R89 800 000 of plant into the building

Negotiating leverage exists only before the plant is installed. A purchase option is close to unobtainable at renewal

Committed R12 000 000 revolver

Year 2 working capital

Sought when Year 2 needs it, it will be priced against a business below covenant. Committed at first close it costs a facility fee

FSSC 22000 or BRCGS certification

Retail-bound and export volume

Not a differentiator but the price of entry. Requires twelve months of operating records

13.3 Conditions precedent to drawdown

13.4 Operating milestones after commissioning

Milestone

Target date

Measure

Consequence if missed

First pallets received

Month 17

Plant validated, temperature pull-down complete, WMS live

Every month of delay is roughly R1.9 million of fixed cost against no revenue

Anchor tenants in occupation

Month 18

1 200 positions occupied under contract

The Year 1 ramp assumption fails at its starting point

32% occupancy

Month 6 of trading

Weekly occupancy report

Trigger point: freeze vehicle purchases and all discretionary capital

FSSC 22000 or BRCGS certification

Month 12 of trading

Certificate issued

Retail-bound and export volume is unavailable; the addressable market narrows sharply

40% average occupancy

Month 12 of trading

Twelve-month average

Trigger point: formal lender review

Blast tunnel utilisation above 35%

Month 18

Tonnes processed against 40 tonnes a day capacity

The premium service is not selling; review pricing and whether capacity was over-specified

Debt service cover above 1.00x

Month 24

Rolling twelve-month EBITDA against service

Trigger point: approach lenders for restructuring before breach

68.9% occupancy

Year 3

Weekly occupancy report

The 1.30x covenant is not met even on a Year 3 test

The occupancy milestones are deliberately set below the plan rather than at it. A business that treats its plan as its floor has no early warning system; one that sets its triggers a few points below has time to act. Each of the four occupancy triggers above corresponds to a committed response in Section 12.4, agreed as board policy before drawdown.

13.5 Where the eighteen months before commissioning go

A funder reviewing this programme should understand that the seventeen months between inception and commissioning are not slack. Three activities run in parallel and each has a hard dependency that cannot be compressed.

Activity

Duration

Why it takes this long

What happens if it is rushed

Anchor tenancy contracting

Months 0 to 11

A six to nine month sales cycle into food manufacturers and protein importers, each of whom is displacing an incumbent arrangement

Positions are contracted at whatever rate is available rather than at the rate card, permanently impairing the revenue base

Ammonia MHI approval

Months 2 to 7

A statutory process requiring a risk assessment, an emergency plan tested with the local authority and competent-person sign-off

Commissioning slips by months against a fixed lease and a fixed interest bill

Construction and commissioning

Months 7 to 17

Envelope, plant installation, ammonia charge, pull-down and validation, each dependent on the previous

Validation failures discovered after product is in the chamber rather than before

The critical path runs through the ammonia approval, not through construction. That is the finding a developer used to conventional industrial fit-out most often misses, and it is why the approval is placed early in the programme and treated as a gate rather than as a parallel workstream. A refrigeration contractor can compress a build; nobody can compress a regulator.