CrystalClean Services — Implementation Gantt Chart

The following implementation plan outlines the key activities, milestones, and workstreams to be completed during Year 1 of operations. Delivery accountability sits with the respective functional leader indicated in the Category column.

CrystalClean Services (Pty) Ltd Business PlanSection 18 › Implementation Gantt Chart

Section 18 · Business Plan

Implementation Gantt Chart

The following implementation plan outlines the key activities, milestones, and workstreams to be completed during Year 1 of operations. Delivery accountability sits with the respective functional leader indicated in the Category column.

The following implementation plan outlines the key activities, milestones, and workstreams to be completed during Year 1 of operations. Delivery accountability sits with the respective functional leader indicated in the Category column.

Activity / Milestone Category M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
Company Registration & CIPC Filing Setup
Secure Office Premises (Sandton) Setup
Banking & Tax Registration (SARS) Setup
Equipment Procurement Operations
Vehicle Acquisition & Branding Operations
Recruit & Screen Cleaning Staff HR
Staff Training Programme HR
Uniform & PPE Procurement HR
Website & Digital Presence Launch Marketing
Corporate Sales Outreach & Tenders Marketing
Social Media Campaign Marketing
First Commercial Contracts Signed Revenue
Residential Service Launch Revenue
Quality Management System Setup Operations
ISO/OHSAS Compliance Review Compliance
Financial Reporting System (Xero) Finance
Mid-Year Performance Review Finance
Year 1 Audit & Investor Report Finance

Key Milestones

Milestone Target Date Owner Success Criteria
Company Registered (CIPC) Week 2 — March 2025 MD Registration certificate received
Seed Capital Received Month 1 — March 2025 MD + Investor ZAR 1.8M in company bank account
Equipment & Vehicles Acquired Month 2 — April 2025 Operations Director All items received, tested, and operational
Full Team Recruited & Trained Month 4 — June 2025 Operations Director 29 staff fully trained and deployed
First Commercial Contract Signed Month 4 — June 2025 MD Minimum 1 contract ≥ ZAR 15,000/month
5 Commercial Contracts Active Month 6 — August 2025 MD ZAR 80,000+ monthly recurring revenue
Website & Digital Presence Live Month 3 — May 2025 Admin Team Website live; LinkedIn and social pages active
Cash-Flow Break-Even Achieved Month 8 — October 2025 CFO / MD Monthly operating CF turns positive
VAT Registration Filed Month 9 — November 2025 CFO SARS VAT number issued
Year 1 Audit Commenced Month 12 — February 2026 CFO + Auditors External audit engagement letter signed
Year 1 Investor Report Issued Month 12 — February 2026 MD Report distributed to all shareholders