SA Best Peanut Butter Business Plan — Implementation Roadmap

The phases from plant construction and certification to two-shift operation, dependencies, and the gate at each stage.

Implementation Roadmap

Jump to section
On this page

  • 12.1 Development programme
  • 12.2 Critical dependencies
  • 12.3 Conditions precedent to drawdown
Implementation roadmap — certify before the first commercial batch
Figure 24. Implementation roadmap — certify before the first commercial batch.

12.1 Development programme

Phase

Activities

Duration

Gate — do not proceed without

1. Site and approvals

Factory lease, zoning, effluent permit, Certificate of Acceptability application

3 months

Municipal approvals confirmed in principle

2. Supply contracting

Supplier qualification, audits, kernel contracting with certificates of analysis

3 to 4 months

70% of Year 1 kernel requirement contracted

3. Customer commitment

Private label negotiation, own-brand listing presentations

4 to 6 months

50% of Year 1 volume committed

4. Construction

Building fit-out, line installation, laboratory, utilities

6 to 8 months

Fixed-price contracts with retention

5. Commissioning

Trial production, shelf-life testing, sensory panels, line validation

2 months

Aflatoxin results consistently below 4 parts per billion on trial batches

6. Certification

FSSC 22000 audit, retailer technical audits, recall test

2 months

Certification achieved and recall procedure tested end to end

7. Ramp

One shift to two; own-brand listings built out

Years 1 to 3

Second shift added in Year 2 against contracted volume

12.2 Critical dependencies

Dependency

What it gates

Why it cannot be accelerated

Contracted kernel supply with certificates of analysis

The control programme and the economics

Kernels are 45.4% of revenue and supplier qualification takes an audit cycle, not a purchase order

Certificate of Acceptability and business licence

Any production at all

Regulation R638 requires inspection of a completed premises

FSSC 22000 certification

Retail and private label listings

An audit assesses a system in operation; certification cannot precede trial production

Private label commitment for half of Year 1 volume

Filling the plant

Fixed costs are R15 690 142 from day one and own-brand listings take longer than the plant takes to build

Aflatoxin results below 4 ppb on trial batches

Commercial production

The internal limit is the control. A plant that cannot hold 4 will not hold 10

Retail listing fees committed

Shelf space

Listings are bought, not won, and R3 600 000 is required before a jar is sold

Working capital facility committed at drawdown

Trading through the ramp

Retail chains pay in 48 days and kernels are held for 42; the facility is drawn to R25 689 744

Second-shift volume contracted

The second shift

It adds R2 700 000 of fixed cost. Adding it before demand exists deepens the loss

12.3 Conditions precedent to drawdown